Question:

You have a large, multi-year project. Because of the large scope and duration, you decide that you will plan near term work in detail, and for the rest, you will make a high-level plan. Once you move ahead you will plan, in detail, for that work. This is an example of:
  • Rolling wave planning
  • Ball park planning
  • Near wave planning
  • Just in Time