IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Project information has been distributed according to the communications management plan. Some project deliverables have been changed in accordance with the project management plan. One stakeholder expressed surprise to the project manager upon hearing of a previously published change to a project deliverable. All stakeholders received the communication containing notification of the change. What should the project manager do?
  1. Determine why the stakeholder did not receive the information and let him know when it was published.
  2. Ask the functional manager why the stakeholder did not understand his responsibility.
  3. Review the communications management plan and make revisions if necessary.
  4. Address the situation in the next steering committee meeting so others do not miss published changes.






Q2. The client informs you that he noticed some parts of the work are not being completed by your team. You ensure him you will look into it and give a proper response after verifying the facts. Which document will you refer to verify it?

  1. Scope statement
  2. WBS dictionary
  3. Schedule baseline
  4. WBS
Correct Answer

Q3. As the project manager, you are considering tools and techniques to help control changes to the project schedule. Which of the following would be acceptable options?

  1. An online system that routes change requests to the appropriate levels for authorization
  2. A paper form that requires a project stakeholder to submit the request in duplicate to the project manager for approval
  3. A system that allows rapid approval of all submitted changes
  4. An online system that routes changes manually to each required approver followed by impact analysis
Correct Answer

Q4. A team member notifies you that she has added extra functionality to the project. She tells you there was no impact on the cost or schedule. What should be done as a result of this change?

  1. Implement change control processes to track the change
  2. Understand what functionality was added
  3. Instruct the team member to remove the extra functionality
  4. Issue an approved change request
Correct Answer

Q5. A project manager in a seller organization discovered that certain deliverables had been delivered to the buyer without undergoing proper testing. Recalling the deliverables will result in a cost overrun on the project. What should the project manager do in such a case?

  1. Recall the deliverables even though there will be a cost overrun.
  2. Terminate the project.
  3. Approach management to obtain additional funding to handle the potential cost overrun.
  4. Wait for the procuring organization to get back with their list of defects in the deliverables.
Correct Answer

Q6. You receive 25 new computers from the seller, but were expecting only 20. In looking at the contract, you see that it says “sellers to provide twenty (20) computers.” What should you do FIRST?

  1. Issue a change order through the contract manager
  2. Return the five extra computers
  3. Make payment for the 25 computers
  4. Call the seller and ask for clarification
Correct Answer

Q7. If earned value (EV) = 35o, actual cost (AC) = 400, planned value ((PV) = 325, what is the cost variance (CV)?

  1. 350
  2. -75
  3. 400
  4. -50
Correct Answer

Q8. A change control system should be created:

  1. As needed on the project
  2. By management
  3. As a formal documented procedure
  4. By the team 4
Correct Answer

Q9. You have recently joined a new company as a project manager. While reviewing the procurement plans for a project you will be taking over, you see that the company is considering using one of the most expensive manufacturers to provide certain equipment required for the project. At your previous employer, you had used a different supplier for the same equipment and had paid significantly less. Without telling your boss, you now call that supplier for a quote. Have you violated the rule of keeping proprietary information confidential?

  1. Maybe. You need to talk to your boss first.
  2. No. There is no harm in sharing the information with your current employer, because you are no longer working for your old employer.
  3. Yes. The supply source is proprietary information, and you should not contact the supplier.
  4. You have not violated any rule.
Correct Answer

Q10. Risk tolerances are determined in order to help:

  1. The team rank the project risks
  2. The project manager estimate the project
  3. The team schedule the project
  4. Management know how other managers will act on the project.
Correct Answer










User Agreement| |Privacy Policy