Question:

Which of the following is the BEST thing to do to try and complete a project two days earlier?
  1. Tell senior management that the project’s critical path does not allow the project to be finished earlier
  2. Tell your boss
  3. Meet with the team and look for options for crashing or fast tracking the critical path.
  4. Work hard and see what the project status is next month






Q2. If a project manager is completing detailed estimating, which type of estimating is MOST likely being used?

  1. Bottom-up
  2. Analogous
  3. Parametric
  4. 50/50 rule 20
Correct Answer

Q3. A WBS is BEST described as a tool for tracking:

  1. The schedule.
  2. Resources
  3. Cost
  4. Scope
Correct Answer

Q4. The project statement of work is a narrative description of products, services, or results to be delivered by a project. The procurement statement of work includes:

  1. Project scope statement
  2. WBS dictionary
  3. WBS
  4. None of the above
Correct Answer

Q5. A parking lot fencing project was bid at US $11 per foot, and one company is doing all the work. The parking lot has four equal sides of 125 feet and requires the installation of a six-foot diameter culvert on one side. Fencing should be installed at a rate of 100 feet per day. The culvert installation will cost US $500 and take one day to complete. The culvert must be installed before work can begin on that side of the fence. After three days of work, one side is complete, another project has 75 feet installed, and the culvert is completely installed. What is the current status of the project?

  1. The budget is neutral with a cost variance of $0
  2. It is over budget, with a cost variance of -$1,100.
  3. It is under budget, with a cost variance of +$500 due to the completion of the culvert installation
  4. It is over budget with a cost variance of +$125.
Correct Answer

Q6. Robert wants to assign a risk owner for every project risk for which a risk response action is planned. Where must he update this information?

  1. Resource management plan
  2. Risk register
  3. Stakeholder register
  4. Project charter
Correct Answer

Q7. As project manager, you would like to show the relationship between two variables to help your project team understand the quality impact better. Which tool should you use?

  1. Scatter Diagram
  2. Run Chart
  3. Fishbone Diagram
  4. Pareto Chart
Correct Answer

Q8. All of the following could occur during the Close Process or Phase process EXCEPT:

  1. Creating lessons learned
  2. Formal acceptance
  3. Reducing resource spending
  4. Performing benefit cost analysis
Correct Answer

Q9. Which of the following is generally the MOST CORRECT use of a project network diagram?

  1. Showing the project schedule
  2. Documenting activity interdependencies
  3. Defining project resources
  4. Defining project costs
Correct Answer

Q10. Which of the following is an output of the Create WBS process?

  1. Scope baseline
  2. Project scope statement
  3. Decomposition
  4. Requirements documentation
Correct Answer