IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A project team is having difficulty communication over long distances. There were 13 team members from two countries, and then 5 people from India were added. This is of concern to the project manager because:
  1. Communications channels grow rapidly.
  2. It will be harder to use reward power.
  3. Communication blockers grow linearly.
  4. Conflict can be increased with an increase in project priorities.






Q2. As project manager o a project, you just handled a risk event that impacted the project cost and schedule. Because the impact is 15 percent total project cost, what is the MOST appropriate action?

  1. Control the cost
  2. Inform the appropriate stakeholders
  3. Act to bring the cost of the event within acceptable limits
  4. Update the project budget.
Correct Answer

Q3. Which of the following is not an interpersonal skill that the project manager will use to manage stakeholders' expectations?

  1. Active listening
  2. Overcoming resistance to change
  3. Punishment
  4. Building trust
Correct Answer

Q4. Extensive use of _____ communication is MOST likely to aid in solving complex problems.

  1. verbal
  2. written
  3. formal
  4. non-verbal
Correct Answer

Q5. Which of the following is not a tool or technique of the Control Procurements process?

  1. Expert judgment
  2. Advertising
  3. Claims administration
  4. Inspection
Correct Answer

Q6. Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?

  1. Eliminate risks in estimates and re-estimate.
  2. Meet with the sponsor to find out what work can be done sooner.
  3. Cut quality.
  4. Decrease scope.
Correct Answer

Q7. A buyer and seller set the rates for junior engineers, senior engineers, architects, and other predefined roles. In what type of contract would this be applicable?

  1. Fixed-price with economic price adjustment contract
  2. Fixed-price incentive contract
  3. Fixed-price contract
  4. Time and material contract
Correct Answer

Q8. Which of the following is TRUE of inspections?

  1. They may not be conducted by the project team.
  2. They test future desires of prospective customers.
  3. They can only be conducted on the final product.
  4. They prevent defective deliverables from reaching the customer.
Correct Answer

Q9. Teams go through various stages of development. According to the Tuckman ladder of development, the stage during which the least amount of work gets done is usually the:

  1. Storming phase
  2. Forming phase
  3. Norming phase
  4. Performing phase
Correct Answer

Q10. Cost of quality includes all costs incurred over the lifetime of the product by investing in the prevention of nonconformance to requirements, appraising the product or service for conformance to requirements, and failing to meet requirements. Which is not an example of the cost of non-conformance?

  1. Rework
  2. Scrap
  3. Liabilities
  4. Destructive testing loss
Correct Answer










User Agreement| |Privacy Policy