IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

There have been numerous changes on your project. All approved changes are BEST reflected in the:
  1. Performance measurement variance
  2. Validate Scope process
  3. Change control procedures
  4. Project management plan






Q2. All of the following are common results of risk management EXCEPT:

  1. Contract terms and conditions are created
  2. The project management plan is changed
  3. The communications management plan is changed
  4. The project charter is changed.
Correct Answer

Q3. Robert is managing a road construction project. Due to unseasonal weather conditions, the team productivity might be above or below target. This is an example of:

  1. Ambiguity risk
  2. Variability risk
  3. Mitigated risk
  4. Opportunity risk
Correct Answer

Q4. The project manager on a large software installation project is working with her team on a critical set of activities. They are working late on Saturday night. Circumstances create the wherein the project manager must decide to change the schedule that will push the end date of the project out two weeks. What has MOST likely happened?

  1. An emergency project change has taken place.
  2. Scope creep has occurred
  3. A status change to the implementation has taken place.
  4. Risk assessment failure has taken place
Correct Answer

Q5. Nate is the project manager for a research and development project. According to the project communication management plan, Nate has to call in weekly project progress update meetings. The last few meetings were a disaster since more time was spent in arguments and less on decisions. Which of the following techniques does Nate need to quickly acquire?

  1. Presentation techniques
  2. Listening techniques
  3. Writing style
  4. Meeting management techniques
Correct Answer

Q6. You are in the middle of a new product development project for your publicly traded company when you discover that the previous project manager made a $3,000,000 payment that was not approved in accordance with your company policies. Luckily, the project cost performance index (CPI) is 1.2. What should you do?

  1. Put the payment in an escrow account.
  2. Bury the cost in the largest cost center available.
  3. Ignore the payment
  4. Contact your manager
Correct Answer

Q7. A software system was accepted by the customer, but has found to give unexpected results. Which of the following BEST describes what the project manager should do FIRST?

  1. Review the customer’s inspection process
  2. Change the activity sequencing
  3. Apologize to the customer
  4. Review the Validate Scope process.
Correct Answer

Q8. You have been just assigned to take over a project from another project manager who is leaving the company. The previous project manager tells you that the project is on schedule, but only because he has constantly pushed the team to perform. What is the FIRST thing you should do as the new project manager?

  1. Check risk status.
  2. Check cost performance.
  3. Determine a management strategy.
  4. Tell the team your objectives.
Correct Answer

Q9. Using the chart, what is the lowest cost of crashing this project to save four weeks?

  1. $18,000
  2. $6,000
  3. $7,000
  4. $9,000
Correct Answer

Q10. A project team member has been having a big disagreement with another team member for over two months when the other team members become involved. The issues are complex, but you have specific experience in the area and know what needs to be done. The BEST choice would be to:

  1. Make the decision yourself
  2. Strive for fair resolution of the issue
  3. Ask the other team members to stay out of the issue
  4. Bring the team together and work out the issue to a win-win solution.
Correct Answer










User Agreement| |Privacy Policy