IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Integration is done by the:
  1. Project manager
  2. Team
  3. Sponsor
  4. Stakeholders






Q2. Risk response owners can potentially have conflict with risk auditors because risk auditors:

  1. Report to the project manager
  2. Investigate the effectiveness of the risk response owner
  3. Measure the effectiveness of the risk thresholds.
  4. Report to the stakeholders
Correct Answer

Q3. With a growing awareness of so-called unknowable-unknowns, the existence of emergent risk is becoming clear. These are risks that can only be recognized after they have occurred. Emergent risks can be tackled through developing:

  1. Project resilience
  2. Project charter
  3. Project management plan
  4. Project risk management plan
Correct Answer

Q4. You are working on a project to build a canal for irrigation purposes. Six months have passed, and now the team is working as a well-organized unit. Team members are interdependent, working smoothly, and working effectively. What team formation stage is this?

  1. Performing
  2. Storming
  3. Norming
  4. Forming
Correct Answer

Q5. The Work Breakdown Structure (WBS) is a deliverable-oriented hierarchical decomposition of the work the project team will execute to accomplish the project objectives and create required deliverables. The Create WBS process falls under which knowledge area?

  1. Project Schedule Management
  2. Project Integration Management
  3. Project Scope Management
  4. Project Cost Management
Correct Answer

Q6. To help the project team function more efficiently on complex and interrelated activities, the project manager decides to use a war room. What does this mean?

  1. All the project records are kept in many locations
  2. The tools needed to accomplish the work are kept in one place with easy access by the team from various locations.
  3. The entire team is located in one area.
  4. The project’s entire senior management team is located in one area.
Correct Answer

Q7. You are a project manager for a small construction project. Your project was budgeted for US $72,000 over a six week period. As of today, you’ve spent US $22,000 of your budget to complete work that you originally expected would cost US $24,000. According to your schedule, you should have spent US $30,000 by this point. Based on these circumstances, your project could be BEST described as:

  1. Under budget
  2. Over budget
  3. On budget
  4. Not having enough information provided.
Correct Answer

Q8. You have been assigned to manage the development of an organization’s new website. The site will be highly complex and interactive, and neither your project team nor the client has much experience with this type of website development. The timeline is extremely aggressive. Any delay will be costly for both your firm and the client. You have a project sponsor and have achieved agreement and sign-off on both the project charter and the project management plan. Client personnel have been kept fully informed of the project's progress through status reports and regular meetings. The project is on schedule and within budget, and a final perfunctory review has been scheduled. Suddenly you hear that the entire effort may be cancelled because the product being developed is totally unacceptable. What is the MOST likely cause of this situation?

  1. A key stakeholder was not adequately involved in the project.
  2. The project charter and project management plan were not thoroughly explained to or adequately reviewed by the client.
  3. Communications arrangements were inadequate and did not provide the required information to interested parties.
  4. The project sponsor failed to provide adequate support for the project.
Correct Answer

Q9. A project manager and her team worked together to develop a work breakdown structure. However, it seems project team members are doing work that is not included in the work breakdown structure. The purpose of a work breakdown structure is to:

  1. Guide the cost estimate for a project, not how the work is done.
  2. Provide senior management with a high level view of the project scope.
  3. Include the work required to create the products of the project.
  4. Include the total project scope or all of the work that must be done to complete the project.
Correct Answer

Q10. Your project is running late and you are over budget. You review the situation and find that it would be difficult for you to complete the project with the given budget. You inform management and they ask you to come up with a new budget. After estimating the new cost, you inform management that you may need 10,000 USD more to complete the project. This is an example of:

  1. Forecast analysis
  2. Status report
  3. Change request
  4. Progress report
Correct Answer










User Agreement| |Privacy Policy