Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Identifying and documenting the specific activities that must be performed to produce work packages is called:
  1. Define Scope
  2. Decomposition
  3. Define Activities
  4. Sequence activities






Q2. Some of your team members do not come to meetings on time. A few other members keep themselves busy with other activities during meetings, and their behavior is not proper. Therefore, to improve the environment what step will you take?

  1. Co-locate team members
  2. Bring them into the war room
  3. Warn them, and if they don’t listen, punish them
  4. Implement ground rules
Correct Answer

Q3. Adam has just taken over a construction project. The project is currently in the planning phase of the project lifecycle. Adam’s next deliverable is to produce an effective stakeholder engagement strategy. Which of the following is the most important component of an effective stakeholder engagement plan?

  1. Management style
  2. Risk tolerance
  3. Construction know-how
  4. Communications
Correct Answer

Q4. Which of the following is not an enterprise environmental factor influencing the Develop Project Management Plan process?

  1. Project management body of knowledge
  2. Governmental or industry standards
  3. Project Management Plan template
  4. Legal and regulatory requirements
Correct Answer

Q5. A responsibility assignment matrix shows all of the following EXCEPT:

  1. Time.
  2. Resources
  3. Names.
  4. Work packages
Correct Answer

Q6. A project manager has just completed subjectively evaluating risks on the project. Which of the following is the MOST important output of this process?

  1. Decrease in the risk ranking for the project
  2. A determination of which risks to process further and which to simply document
  3. Probabilistic analysis of the project and identification of risk triggers
  4. Probability of achieving cost objectives.
Correct Answer

Q7. You are the project manager for one part of a new program in your organization. You are four months into a three-year project when your project team makes significant discoveries on your project. What is the BEST thing to do?

  1. Make certain the discoveries are included in the project lessons learned
  2. Make certain the discoveries are in the monthly status report.
  3. Make certain you mention the discoveries at the senior management meeting in two months
  4. At the weekly meeting, make certain you tell the other project managers involved in this program about the discoveries.
Correct Answer

Q8. Various tools and techniques determine project requirements during the Collect Requirements process. These requirements form the basis for defining the project scope. One of the responsibilities of a project manager is to identify key project deliverables during this exercise. Where are the key project deliverables documented?

  1. Scope Management Plan
  2. Requirements Management Plan
  3. Project Scope Statement
  4. Accepted Deliverables
Correct Answer

Q9. Jijo and Stefan are two employees of your organization. Jijo is working in an office and Stefan is on a site so their working conditions are different. During the project execution, both of them have some kind of conflict and come to you. You listen to them and solve the conflict. Which of the following is most likely to be a reason for a conflict in the working environment?

  1. Ground rules
  2. Personal work style
  3. Salary
  4. Working conditions
Correct Answer

Q10. Based on the chart, how many weeks will this project take?

  1. 16
  2. 31
  3. 18
  4. 13
Correct Answer