IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Using the chart, the resource for activity A is assigned to an additional, more important, project. As a result, the resource will not be able to devote as much time to your project. Activity A will now take 10 weeks. How does this affect the project?
Project Management PMP-5009.jpg
  1. There are three critical paths.
  2. The project will be delayed
  3. The project is riskier
  4. Activity D will be delayed






Q2. You are reviewing a chart which looks like an S-Curve during the execution phase of your project. What kind of chart is this?

  1. Cause and effect diagram
  2. Pareto diagram
  3. Cost baseline
  4. Sensitivity diagram
Correct Answer

Q3. “Do the work because I have been put in charge!” is an example of what type of power?

  1. Formal
  2. Penalty
  3. Effective
  4. Expert.
Correct Answer

Q4. If the team cannot identify a suitable response to identified risk, which risk response strategy, would they apply?

  1. Transference.
  2. Acceptance.
  3. Mitigation.
  4. Avoidance
Correct Answer

Q5. Work Performance Data is an important input to the Control Procurements process. Which of the following is not a component of Work Performance Data?

  1. Data regarding supplier’s conformance to quality standards
  2. Data on completed deliverables
  3. Data regarding incurred or committed costs on each supplier contract
  4. Data on supplier invoices and respective payments
Correct Answer

Q6. Which of the following is an example of rolling wave planning in a project following an adaptive life cycle?

  1. Iterative scheduling with a just-in-time log
  2. Predictive scheduling with no backlog
  3. Inflexible scheduling without leads and lags
  4. Iterative scheduling with a backlog
Correct Answer

Q7. If a project has a 60 percent chance of a $100,000 profit and a 40 percent chance of a $100,000 loss, the expected monetary value of the project is:

  1. $20,000 profit
  2. $40,000 loss
  3. $100,000 profit
  4. $60,000 loss
Correct Answer

Q8. When entering into procurement, it is BEST to assume there will be disputes about the performance of the work as specified, and to:

  1. Include a procedure in the contract describing the means for dispute resolution
  2. Track claims to ensure the best position during litigation
  3. Make sure disputes are never brought to public knowledge
  4. Include a change order provision in the contract.
Correct Answer

Q9. Which of the following is not a tool or technique of the Control Procurements process?

  1. Expert judgment
  2. Advertising
  3. Claims administration
  4. Inspection
Correct Answer

Q10. Your company is way behind schedule in the deployment of a government-mandated change to a health care processing system that must be in production by the end of the year. To meet the due date, you and your team have met and decided to hire an additional 50 programmers to work with the existing staff. This is an example of what?

  1. Resource Leveling
  2. Fast Tracking
  3. Crashing
  4. Risk Transference
Correct Answer










User Agreement| |Privacy Policy