Project Management - Question 1:

Product verification is different than scope verification in that product verification:

  1. Occurs during the executing process group
  2. Verifies that the correct products have been used
  3. Obtains customer sign-off
  4. Makes sure all work is completed satisfactorily.






Project Management- Q2. You are in the identifying risks process. You are meeting with your team members and stated that the project may be delayed because of the late delivery of certain consumables for your project. Now you ask the team members to find ways in which this problem can occur. What technique are you using here?

  1. Assumption and constraint analysis
  2. Brainstorming
  3. Sensitivity analysis
  4. Root cause analysis
Correct Answer


Project Management- Q3. Creating a sense of community is a benefit of what type of strategy?

  1. Group-based management
  2. Hoteling
  3. Co-location
  4. Virtual teams
Correct Answer


Project Management- Q4. In which project management process group is the project manager likely to do more directing?

  1. Initiating
  2. Planning
  3. Executing
  4. Monitoring and controlling
Correct Answer


Project Management- Q5. You are managing the project when you discover an estimated completion date will occur after the desired date. What should you do FIRST?

  1. Add resources to the project.
  2. Evaluate the possibility of doing more activities in parallel.
  3. Negotiate for more time
  4. Explain to the customer that the project cannot be done on schedule.
Correct Answer


Project Management- Q6. The project work has begun when the project manager notices how many times meetings and discussions are disrupted by power outages and the lack of a warm place to meet. She turns her attention to influencing the organization to improve the team’s working conditions. She is following the concepts of which motivational theorist?

  1. Herzberg
  2. McGregor
  3. Theory Y
  4. Maslow’s hierarchy
Correct Answer


Project Management- Q7. All of the following are parts of an effective change management plan EXCEPT:

  1. Procedures
  2. Standards for reports
  3. Meetings
  4. Lessons learned
Correct Answer


Project Management- Q8. Lena is managing the construction of a new office facility for her company. The project is halfway through the execution. The project sponsor has asked Lena to ensure that all key project stakeholders are still committed to the project. How can Lena assess the stakeholders' current engagement levels?

  1. By analyzing the most recent issue register
  2. By reviewing the Stakeholders Engagement Assessment Matrix last updated during the planning phase of the project
  3. By requesting the key stakeholders to submit a signed declaration of commitment
  4. By communicating and interacting with the key stakeholders
Correct Answer


Project Management- Q9. As a project manager, you are analyzing the costs incurred in a project. Which of the following costs cannot be classified under cost of nonconformance?

  1. Quality Assurance Costs
  2. Warranty costs
  3. Costs due to loss of reputation
  4. Rework costs
Correct Answer


Project Management- Q10. If a process has a lack of consistency and predictability it is said to be:

  1. In control
  2. Quality assured
  3. Out of control
  4. Assigned a cause
Correct Answer