IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

The project was going well when all of a sudden there were changes to the project coming from multiple stakeholders. After all the changes were determined, the project manager spent time with all the stakeholders to find out why there were changes and to discover any more. The project work has quieted down when a team member casually mentions to the project manager that he added functionality to a product of the project. Do not worry he says, “I did not impact time, cost, or quality!”
  1. Ask the team member how the need for functionality was determined
  2. Hold a meeting to review the team member’s completed work
  3. Look for other added functionality.
  4. Ask the team member how he knows there is no time, cost, or quality impact.






Q2. The project charter is the document that authorizes the existence of the project and contains a great deal of important information. Which of the following options shows the correct content of a project charter?

  1. Project purpose, high level requirements, assumptions and constraints, summary budget
  2. High-level risk, summary milestone, project management plan, summary budget
  3. Project objective, stakeholder list, WBS, project approval authority
  4. Name of the sponsor, name of the project manager, schedule baseline, summary budget
Correct Answer

Q3. An estimating technique that uses a statistical relationship between historical data and other variables (such as square footage in construction or lines of code in software development) is known as:

  1. Parametric Estimating
  2. Analogous Estimating
  3. Bottom-up Estimating
  4. Historical Analysis
Correct Answer

Q4. A project involved development of a high-speed, hard disk drive. As part of its testing, the hard disk was subjected to continuous operation at a high speed and an elevated temperature. At the end of the test, the hard disk was destroyed beyond use. The cost of such testing is usually classified as:

  1. Appraisal costs
  2. Internal failure costs
  3. Cost of nonconformance
  4. Prevention costs
Correct Answer

Q5. What is the primary risk when including reserves, or contingency allowances, in your cost estimate?

  1. Cancelling your project
  2. Understating the cost estimate
  3. Overstating the cost estimate
  4. Tracking the funds
Correct Answer

Q6. While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?

  1. Start-to-Finish
  2. Start-to-Start
  3. Finish-to-Start
  4. Finish-to-Finish
Correct Answer

Q7. You just found out that a major subcontractor for your project consistently delivers items late. You decide to postpone dealing with the issue until you have more time. What conflict resolution method are you using?

  1. Ignoring
  2. Compromise
  3. Smoothing
  4. Withdrawal.
Correct Answer

Q8. The Create WBS process identifies the deliverables at the __________ level in the Work Breakdown Structure (WBS).

  1. Lowest
  2. Any
  3. Tenth
  4. Highest
Correct Answer

Q9. Residual risks are risks that remain after risk response planning. Secondary risks are:

  1. Planning risks that are no longer a factor during project executing
  2. Discovered during risk identification
  3. New risks created by the risk response strategies selected.
  4. Lower priority risks not requiring mitigation efforts.
Correct Answer

Q10. Which of the following BEST describes the phrase, “influencing the factors that affect change”?

  1. Telling people that changes are not allowed
  2. Determining the sources of changes and fixing the root causes
  3. Adding more activities to the work breakdown structure to accommodate risks
  4. Calculating the impact of changes to date on the project
Correct Answer










User Agreement| |Privacy Policy