Project Management - Question 1:

A change log is an important input to the Manage Stakeholder Engagement process. Which process provides this input?

  1. Plan Communications Management
  2. Manage Communications
  3. Perform Integrated Change Control
  4. Monitor Communications






Project Management- Q2. Miranda is an experienced project manager. As part of the Collect Requirements phase, she decides to use a group creativity technique. This technique is intended to enhance brainstorming with a voting process and can be used to rank the most useful ideas for further brainstorming or prioritization. Which of the following will she likely use?

  1. Normal group technique
  2. Minimal group technique
  3. Unanimous group technique
  4. Nominal group technique
Correct Answer


Project Management- Q3. You are a project manager for a small construction project. Your project was budgeted for US $72,000 over a six week period. As of today, you’ve spent US $22,000 of your budget to complete work that you originally expected would cost US $24,000. According to your schedule, you should have spent US $30,000 by this point. Based on these circumstances, your project could be BEST described as:

  1. Under budget
  2. Over budget
  3. On budget
  4. Not having enough information provided.
Correct Answer


Project Management- Q4. Which of the following activities occurs during the Plan Procurements process?

  1. Make-or-buy decisions
  2. Answering sellers’ questions about the bid documents
  3. Advertising
  4. Proposal evaluation.
Correct Answer


Project Management- Q5. You have recently joined a new company as a project manager. While reviewing the procurement plans for a project you will be taking over, you see that the company is considering using one of the most expensive manufacturers to provide certain equipment required for the project. At your previous employer, you had used a different supplier for the same equipment and had paid significantly less. Without telling your boss, you now call that supplier for a quote. Have you violated the rule of keeping proprietary information confidential?

  1. Maybe. You need to talk to your boss first.
  2. No. There is no harm in sharing the information with your current employer, because you are no longer working for your old employer.
  3. Yes. The supply source is proprietary information, and you should not contact the supplier.
  4. You have not violated any rule.
Correct Answer


Project Management- Q6. A project manager knows that she can delay the start of certain activities within the project schedule to coincide with the mitigation of a known risk. She knows exactly the work and duration needed, should the risk event occur. She is confident that the finish date will not be impacted by the time delay. Which of the following aspects of schedule development has the project manager used in this situation?

  1. She has relied on her certainty that, for risk planning purposes, assumptions are considered to be true, real or certain.
  2. GERT probability factors provide her with certainty that there will be activities in the current schedule that will not be performed at all.
  3. Her float calculations have revealed those activities that allow sufficient time for the inserted activities.
  4. The project manager’s risk management plan was to build in buffer time to all the project activities during schedule development in order to cover any risk event occurrence
Correct Answer


Project Management- Q7. Which of the following BEST describes when the baseline can be changed?

  1. Only under emergency conditions
  2. The original baseline is always maintained throughout the project
  3. With any approved changes
  4. When the project sponsor determines it is appropriate
Correct Answer


Project Management- Q8. Analogous estimating:

  1. Uses bottom-up estimating techniques
  2. Is used most frequently during the executing processes o the project.
  3. Use top-down estimating techniques
  4. Uses actual detailed historical costs
Correct Answer


Project Management- Q9. Which of the following tools helps you to determine whether the subcontractor’s work is meeting the quality requirements?

  1. Quality control
  2. Quality audit
  3. Inspection of deliverables
  4. Delphi technique
Correct Answer


Project Management- Q10. All of the following are part of the Perform Quality Control process EXCEPT:

  1. Pareto chart
  2. Control charts
  3. Inspection
  4. Quality audits.
Correct Answer