Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which statement BEST explains the phrase “Quality is planned in, not inspected in.”
  1. It is more expensive to determine quality by inspection than by planning it.
  2. Quality activities occur during the planning process group of the project
  3. Quality is part of planning, not inspection
  4. Planning for quality is after the fact.






Q2. Which of the following are ALWAYS inputs to the risk management process EXCEPT:

  1. Historical information.
  2. Lessons learned.
  3. Work breakdown structure.
  4. Project status reports.
Correct Answer

Q3. Identification of new risks, reassessment of old risks, and closing of outdated risks are part of the Monitor Risks process. How often should project risk reassessment be scheduled?

  1. It depends on how the project progresses relative to its objectives.
  2. Reassessment is necessary at the 50 percent and 75 percent stages of project completion.
  3. Reassessment is necessary at the 25 percent, 50 percent, and 75 percent stages of project completion.
  4. Reassessment is necessary at the 20 percent, 40 percent, 60 percent and 80 percent stages of project completion.
Correct Answer

Q4. Quality metrics used during the Control Quality process are defined during which process?

  1. Plan Quality Management
  2. Define Scope
  3. Collect Requirements
  4. Manage Quality
Correct Answer

Q5. The work breakdown structure (WBS) does all of the following except

  1. Organizes and defines the entire scope of the project.
  2. Divides the project into smaller, more manageable tasks.
  3. Serves as a high-level planning tool for work planned but not yet approved.
  4. Both A and B.
Correct Answer

Q6. Which of the following processes will determine the correctness of deliverables?

  1. Plan Deliverables
  2. Plan Quality Management
  3. Control Quality
  4. Manage Quality
Correct Answer

Q7. A dependency requiring that design be completed before manufacturing can start is an example of:

  1. Discretionary dependency
  2. External dependency
  3. Mandatory dependency
  4. Scope dependency
Correct Answer

Q8. Another project manager has a family emergency and must leave. He has asked you to fill in for him during a team meeting to discuss a minor problem with the project. He has already distributed a detailed agenda and provided with a copy. When you attend the meeting, several members of the team are making fun of the absent project manager’s ethnic heritage. Your company does not have a formal diversity policy covering such behavior. What should you do?

  1. Because your company does not have a written diversity policy, there is nothing you can do.
  2. Report the incident to the other project manager
  3. Hold the meeting as if nothing happened
  4. Begin the meeting with a discussion of diversity and professional behavior.
Correct Answer

Q9. Which of the following is the BEST method to make reward systems MOST effective?

  1. Pay a large salary increase to the best workers
  2. Give the team a choice of rewards
  3. Make the link between performance and reward clear
  4. Present notification of rewards within the company.
Correct Answer

Q10. Dana works for a federal agency that manages mission critical projects. As a project manager, she is responsible for all communication needs in her data center project, which has started recently. This project involves many stakeholders, customers, external vendors, and team members. Since conflicts are inevitable in such a massive project, she has decided to provide her project team the details of the issue escalation process, including the names of the chain of command to refer issues to that cannot be resolved at a lower level. Where must Dana document the escalation process?

  1. The project charter
  2. The communications management plan
  3. The issue log
  4. The project scope document
Correct Answer