Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You were in the middle of a two-year project to deploy new technology to field offices across the country. A hurricane caused power outages just when the upgrade was near completion. When the power was restored, all of the project reports and historical data were lost with no way of retrieving them. What should have been done to prevent this problem?
  1. Purchase insurance
  2. Plan for a reserve fund
  3. Monitor the weather and have a contingency plan
  4. Schedule the installation outside of the hurricane season.






Q2. You have just joined a new organization as a project manager. You have heard a number of rumors about the procurement manager having possible underhanded dealings with suppliers. However, you have no proof these rumors are true. Your project requires a large number of dump trucks. Company policy mandates that all purchases go through the procurement department rather than the department employees. The value of the dump truck purchase is US$395,000, and the contract went to a supplier your company regularly uses. Shortly after taking delivery of the dump trucks, you learn the procurement manager is driving a new car. What should you do?

  1. Ask the procurement manager about the purchase of her new car
  2. Report this to the appropriate management
  3. Talk to the supplier to find out if there was a bribe involved in the project
  4. Do nothing
Correct Answer

Q3. A change control system should be created:

  1. As needed on the project
  2. By management
  3. As a formal documented procedure
  4. By the team 4
Correct Answer

Q4. What does a resource histogram show that a responsibility assignment matrix does not?

  1. Time
  2. Activities
  3. Interrelationships
  4. The person in charge of each activity
Correct Answer

Q5. A project is considered closed when the:

  1. Client accepts the product
  2. Lessons learned are completed
  3. Archives are completed
  4. Contract is finished
Correct Answer

Q6. Which of the following BEST describes what a network diagram is used for when the work is being completed?

  1. To track the flow of information in system, looking at all the interfaces
  2. To determine if the evaluation criteria should be created before the contract statement of work is written
  3. To see if the cost of a change exceeds the project cost baseline
  4. To evaluate the reward system’s effectiveness 35
Correct Answer

Q7. If you finish your project early, there is a chance that you may get another project, so you are trying very hard to get your project finished. You use fast tracking, crashing, overtime, etc. Which strategy is this?

  1. Exploit
  2. Enhance
  3. Accept
  4. Mitigate
Correct Answer

Q8. The line in the middle of a control chart is called the:

  1. Mean
  2. Specification limit
  3. Rule of seven
  4. Upper and lower control limit.
Correct Answer

Q9. A project has gone out of control, and the project manager is trying to bring it back under control. There have been a number of changes to the project scope. Some of these changes resulted in further changes, causing project cost to spiral upward and causing the project to go out of schedule. This is known as:

  1. Scope creep
  2. Scope jump
  3. Project creep
  4. Scope control
Correct Answer

Q10. Which of the following sequences represents straight line depreciation?

  1. $100, $100, $100
  2. $100, $120, $40
  3. $100, $120, $160
  4. $160, $140, $120
Correct Answer