IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You are working on a waste management project that, upon completion, will be turned over to the local municipality for steady-state operation. Parking of trucks and other vehicles has become a serious problem because no parking area was allotted to you on the main dumping site. As a result, your trucks are parked on nearby roadsides. One of the fleet supervisors informs you that close to the main site, there is a large tract of land a local charity owns. Many locals park their cars on this tract of land. What should you do?
  1. Since the piece of land is already used as parking, you can park your trucks over there.
  2. Don’t park the trucks on that piece of land because it will be a violation of other’s property rights.
  3. Check the local parking laws.
  4. Ask the supervisor to get contact information of the local charity.






Q2. Communications management plans should include all of the following except:

  1. Stakeholder communication requirements
  2. Reasons for information distribution
  3. Escalation process
  4. Risk Register
Correct Answer

Q3. Communication is the key to the success of a project. As the project manager, you have three stakeholders with whom you need to communicate. As such, you have six channels of communication. A new stakeholder has been added that you also need to communicate with. How many communications channels do you have now?

  1. 7
  2. 10
  3. 12
  4. 16
Correct Answer

Q4. How can a project manager ensure continued active support of the project supporters and at the same time minimize negative impacts from the negative stakeholders?

  1. By ensuring that stakeholders clearly understand the communication management plan
  2. By ensuring that stakeholders clearly understand the stakeholder management strategy
  3. By ensuring that stakeholders are kept disengaged throughout the project lifecycle
  4. By ensuring that stakeholders clearly understand project goals, objectives, benefits, and risks
Correct Answer

Q5. A team of experts come to your project and ask for approved procedures to verify your team is following these procedures. This is an example of which of the following?

  1. Quality control
  2. Manage quality
  3. Verify scope
  4. Control scope
Correct Answer

Q6. Which of the following indicates the required cost performance in order to complete the project on budget?

  1. TCPI
  2. CPI
  3. EAC
  4. SPI
Correct Answer

Q7. An activity has been delayed and the project manager needs to deal with the situation. What is the NEXT thing she should do?

  1. Determine how much of a problem it is.
  2. Report to management
  3. Crash or fast track
  4. Use contingency reserves
Correct Answer

Q8. After brainstorming potential project risks, what is the recommended method for prioritizing these risks and their mitigation plans?

  1. RACI chart
  2. Control chart
  3. Fishbone diagram
  4. Probability and impact matrix
Correct Answer

Q9. Which of the following is not a tool or technique of the Control Procurements process?

  1. Expert judgment
  2. Advertising
  3. Claims administration
  4. Inspection
Correct Answer

Q10. Which of the following BEST describes what a network diagram is used for when the work is being completed?

  1. To track the flow of information in system, looking at all the interfaces
  2. To determine if the evaluation criteria should be created before the contract statement of work is written
  3. To see if the cost of a change exceeds the project cost baseline
  4. To evaluate the reward system’s effectiveness 35
Correct Answer










User Agreement| |Privacy Policy