IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Project Management - Question 1:

The client has requested a change in a deliverable which you have processed through a change request and it is approved. Now, you are in the process of implementing this change into the project. In which of the following processes do you implement the approved change?

  1. Monitor and control project work
  2. Direct and manage project work
  3. Perform integrated change control
  4. Control scope






Project Management- Q2. Who is ultimately responsible for quality management on the project?

  1. The project engineer
  2. The project manager
  3. The quality manager
  4. Team member
Correct Answer


Project Management- Q3. You are having difficulty estimating the cost of a project. Which of the following BEST describes the most probable cause of your difficulty?

  1. Inadequate scope definition
  2. Unavailability of desired resources
  3. Lack of historical records from previous projects.
  4. Lack of company processes.
Correct Answer


Project Management- Q4. You are a project manager who is in charge of an important project for your company. The project is 40 percent complete after three months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last eight months. How is the project performing?

  1. The project is behind schedule and over budget.
  2. The project is ahead of schedule and under budget.
  3. The project is behind schedule and under budget.
  4. The project is ahead of schedule and over budget.
Correct Answer


Project Management- Q5. What is the primary risk when including reserves, or contingency allowances, in your cost estimate?

  1. Cancelling your project
  2. Understating the cost estimate
  3. Overstating the cost estimate
  4. Tracking the funds
Correct Answer


Project Management- Q6. Which of the following tools helps in determining the gaps between the current and desired stakeholder engagement levels?

  1. Stakeholder register
  2. Monte Carlo analysis
  3. Stakeholder engagement assessment matrix
  4. Fishbone diagram
Correct Answer


Project Management- Q7. Recommended corrective actions result from which of the following?

  1. Cost aggregation
  2. Bottom-up estimating
  3. Reserve analysis
  4. Control costs.
Correct Answer


Project Management- Q8. What is present value (PV)

  1. Value of assets that a company owns
  2. Today’s value of future cash flows
  3. Future value of money on hand today
  4. Current value of today’s assets adjusted for inflation 9
Correct Answer


Project Management- Q9. Which of these items are important to address when determining each person's role in the project team?

  1. Role, authority, responsibility, and competency
  2. Role, responsibility, and competency
  3. Role and responsibility
  4. Role, authority, and competency
Correct Answer


Project Management- Q10. A list of risks for additional study is an output of:

  1. Identify risks
  2. Plan risk management
  3. Perform Qualitative Risk Analysis
  4. Perform Quantitative Risk Analysis.
Correct Answer











User Agreement| |Privacy Policy
© 2026 - Tag&Link – Mostafa Taha Mohamed