Question:

A first-time project manager was assigned to a project that had a duration of three months. In order to get a head start on the project, the manager took an older, completed the project and incorporated all the tools, techniques, and checklists in their entirety from that project into the current one. The older project was completed in 14 months’ time and was remarkably similar in nature. The most appropriate comment on this would be:
  1. This is an excellent example of re-use of artifacts from prior projects.
  2. This may be unnecessary. The project management team needs to decide what is appropriate for the project.
  3. This is not the correct procedure. The project manager should always create processes and documents afresh for new projects.
  4. This is not correct. The project manager is violating copyright and intellectual property rights of the organization's prior customers.






Q2. Tracey is managing an ERP system implementation project. Which of the following tools can help her uncover a number of hidden process requirements during the Collect Requirements process?

  1. Observation
  2. Questionnaires
  3. Surveys
  4. Nominal group technique
Correct Answer

Q3. You have a US $100,000,000 project that has 34 team members in four different countries. At the completion of project planning, you have identified six risks, 225 work packages, 13 stakeholders and seven phases to the project life cycle. What part of this project management plan needs to be revisited?

  1. The Identify Risks process
  2. The staffing management plan
  3. The network diagram
  4. The communications management plan
Correct Answer

Q4. Andy’s project stakeholders are not happy as the project is lagging behind schedule. During the executive committee meeting, Andy requests all stakeholders to keep their calm as most of the project deliverables have been completed and only quality inspections of these deliverables is pending. He assures the stakeholders that he is planning to crash the project to meet the completion deadline. What should be the stakeholders’ biggest concern now?

  1. Crashing at this stage might result in an exponential cost increase and more time will be required to recover that cost.
  2. Crashing at this stage might result in undetected errors, decreased profits, and increased post-implementation risks.
  3. Why Andy hasn’t chosen to fast-track the project instead of crashing the project.
  4. Stakeholders do not know the PMBOK jargon; crashing is a valid schedule compression technique.
Correct Answer

Q5. In creating a project management plan, how should a project manager use rewards?

  1. Use the reward system currently in place throughout the company.
  2. Ignore rewards because the functional manager will take care of it.
  3. Create a specific reward system for the project.
  4. Ignore rewards because they are management’s responsibility.
Correct Answer

Q6. Which of the following is CORRECT in regard to the Control Scope process?

  1. Effective scope definition can lead to a more complete project scope statement
  2. The Control Scope process must be done before scope planning
  3. The Scope Control process must be integrated with other control processes
  4. Controlling the schedule is the most effective way of controlling scope.
Correct Answer

Q7. There are several communication methods used to share and distribute information to stakeholders, team members, and management. Which of the following communication methods is used when you notify the public about environmental effects from your project after implementation by posting reports on the project's website?

  1. Pull communication
  2. Interactive communication
  3. Informal communication
  4. Push communication
Correct Answer

Q8. A project to design and build a new aircraft is cancelled after the project has been underway for some time. What process is employed to document what work was done and to what extent it was completed?

  1. Validate Scope
  2. Control Scope
  3. Control Quality
  4. Close Project or Phase
Correct Answer

Q9. A change request that is issued to bring the performance of the project back in line with the project management plan is related to:

  1. Corrective action
  2. Defect repair
  3. Proactive action
  4. Preventive action
Correct Answer

Q10. The project budget is proving to be inaccurate. The SPI is 1.1. The team has had a negative deviation from the activity attributes, and the sponsor has inserted herself on the change control board. What is the BEST thing for the project manager to do?

  1. Try to encourage the sponsor to remove herself from the change control board
  2. Re-compute the project schedule
  3. Re-estimate the activity attributes
  4. Calculate the cost performance index
Correct Answer