IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A project manager has just been assigned to a project that has been in progress for two months when a team member requests more time on an activity he is working on. The project manager discovers that the only impact to the project will be a delay on a noncritical path activity. The customer has emphasized the importance of completing the project on schedule. What should the project manager do NEXT?
  1. Submit the information to the change control board, determine if this event might impact the team member’s future work, inform the team member of the board’s decision
  2. Ask the team member why they need more time, begin integrated change control, adjust the project schedule as needed
  3. Look for impacts to quality, cut unneeded scope from the project, ask for more resources
  4. See if any stakeholders object to the change, calculate the exact impact on the project, look at removing this resource from the project






Q2. Which of the following is not an appropriate method for dealing with a negative risk?

  1. Avoid
  2. Exploit
  3. Transfer
  4. Mitigate
Correct Answer

Q3. RACI stands for______________, ________________, ___________, _______________.

  1. Review, Analyze, Calculate, Implement
  2. Responsible, Actual, Complete, Informative
  3. Roles, Activities, Costs, Instructions
  4. Responsible, Accountable, Consult, Inform
Correct Answer

Q4. Many more changes were made to the project during the project executing processes than had been expected. What is the BEST thing for the project manager to do now?

  1. Wait until all changes are known, print out a new schedule, and revise the baseline
  2. Make changes as needed, but maintain a schedule baseline
  3. Make only the changes approved by management
  4. Talk to management before any changes are made
Correct Answer

Q5. Which of the following is the primary output of the Develop Project Team process?

  1. Change requests
  2. Staffing management plan
  3. Team performance assessment
  4. Updated issue log
Correct Answer

Q6. A project manager has just started planning his project. If he has only limited information about the project, he should use the following technique to estimate the duration for each activity using historical data from a similar project:

  1. Four-point estimating
  2. Three-point estimating
  3. Analogous estimating
  4. Parametric estimating
Correct Answer

Q7. Calculating estimate to complete (ETC) is done during the:

  1. Planning process group
  2. Initiating process group
  3. Executing process group
  4. Monitoring and controlling process group.
Correct Answer

Q8. Although the stakeholders thought there was enough money in the budget, halfway through the project the cost performance index (CPI) is 0.7. To determine the root cause, several stakeholders audit the project and discover the project budget was estimated analogously. Although the activity estimates add up to the project estimate, the stakeholders think something was missing in how the estimate was completed. Which of the following describes what was missing?

  1. Estimated costs should be used to measure CPI.
  2. SPI should be used, not CPI
  3. Bottom-up estimating should have been used
  4. Past history was not taken into account.
Correct Answer

Q9. You have two activities with Finish to Start sequences. The duration of the first activity is 10 days, and the duration of the second activity is 8 days. The estimated time completed for these activities is 18 days. The client asks you complete these activities within 15 days; you review his request and agree to do so at no extra cost. Now, you plan to start the second activity three days before the first activity completes so that both activities can be completed in 15 days. This process is known as:

  1. Schedule modification
  2. Fast tracking
  3. Crashing
  4. None of the above
Correct Answer

Q10. A business is considering more than a dozen infrastructure upgrade projects. These projects, once delivered, will add to the organization’s overall performance but will not contribute to any of the revenue streams. Prior to initiating any such project, the value of the project to the organization must be determined. Which of the following is the most important factor to consider in such a scenario?

  1. Net Present Value (NPV) of the projects
  2. Internal Rate of Return (IRR) of the projects
  3. Alignment with the strategic goals
  4. Investment requirement
Correct Answer










User Agreement| |Privacy Policy