A project team is meeting to determine what the selection criteria will be for the project procurement. What procurement process are they in?
  1. Plan Procurement Management
  2. Conduct Procurements
  3. Control Procurements
  4. Close Procurements






Q2. The client has given you a project to install a new kind of elevator, so you start designing it from scratch. The planning phase is completed and you are now about to install the elevator. Suddenly a team member comes to you and asks for a change in the quality management plan as he has identified a flaw in the process. In which process can you perform the integrated change control?

  1. During the monitoring & controlling phase
  2. During the execution phase
  3. Throughout the project
  4. During the executing, and monitoring & controlling phase
Correct Answer

Q3. Which parts of the risk management process use the project scope statement as an input?

  1. Plan Risk Management and Control Risks
  2. Perform Qualitative Risk Analysis and Plan Risk Management
  3. Perform Quantitative Risk Analysis and Plan Risk Responses
  4. Plan Risk Responses and Control Risks.
Correct Answer

Q4. A manager has responsibility for a project that has the support of a senior manager. From the beginning, you have disagreed with the manager as to how the project should proceed and what the deliverables should be. You and she have disagreed over many issues in the past. Your department has been tasked with providing some key work packages for the project. What should you do?

  1. Provide the manager with what she needs
  2. Inform your manager of your concerns to get her support
  3. Sit down with the manager at the beginning of the project, attempt to describe why you object to the project, and discover a way to solve the problem
  4. Ask to be removed from the project.
Correct Answer

Q5. Bill and Jake are two team members in a project. They do not get along well and are constantly involved in verbal conflicts. The project manager understands the characteristics of conflict and the conflict management process and tries to resolve the situation. Which of the following is not a correct statement?

  1. Openness resolves conflict
  2. Conflict is natural and forces a search for alternatives
  3. Conflict is inevitable in a project environment.
  4. The project manager is not responsible for conflict management.
Correct Answer

Q6. You are the Project Manager and are responsible for the development of a mall. As with any construction project, there will be multiple iterations of blueprints and engineering drawings. Therefore, you have decided to create an online database that can be used to query the documents by name, type, date, etc. This is an example of what type of communication tool?

  1. Project Management Information System
  2. Lessons Learned
  3. Project Records
  4. Configuration Management System
Correct Answer

Q7. Velvet is working for a chemical industry, and her management proposed two different projects to manufacture benzene for commercial use. After doing financial analysis, the financial advisor provided her with the following statistics about the projects: Project 1: 60 percent probability of success with a profit of $500,000 and 20 percent probability of failure with a loss of $200,000. Project 2: 30 percent probability of success with a profit of $300,000 and 30 percent probability of failure with a loss of $400,000. Based on the information above, Velvet should choose:

  1. Either project 1 or project 2
  2. Neither project 1 nor project 2
  3. Project 2
  4. Project 1
Correct Answer

Q8. A cost baseline is an output of which cost management process?

  1. Estimate Activity Resources
  2. Estimate Costs
  3. Determine Budget
  4. Control Costs.
Correct Answer

Q9. Conflict management is a tool and technique of which of the following processes?

  1. Control Procurements
  2. Identify Stakeholders
  3. Close Project or Phase
  4. Manage Team
Correct Answer

Q10. A project manager has some authority to manage the budget; however, he does not have any full-time employees under him. In what type of organization is he working?

  1. Strong matrix
  2. Weak matrix
  3. Balanced matrix
  4. Projectized
Correct Answer