IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Project Management - Question 1:

What do the buyer and seller have in common with regard to Control Procurements?

  1. Both parties ensure that they meet their contractual obligations and that their own legal rights are protected.
  2. Both parties have specific resources that can be idle.
  3. Both parties have a contract change management plan.
  4. Each party has its own project plan and legal team.






Project Management- Q2. As an experienced PMP, you have found that running a WBS meeting is tricky because you need to find a balance between insufficient decomposition and excessive decomposition. When items are excessively decomposed, it leads to all the following except:

  1. Breaking the 100 percent rule
  2. Inefficient use of resources
  3. Nonproductive management effort
  4. Decreased efficiency when performing work
Correct Answer


Project Management- Q3. Performance reports should address all the needs of:

  1. Management.
  2. Team members.
  3. The project manager.
  4. Stakeholders.
Correct Answer


Project Management- Q4. In order to provide one of your team members with a reward for excellent performance, you are going to allow him to acquire the new skill in which he is interested. Assuming that any activity shown in the chart would provide the team member with the benefit, which activity would you assign him to?

  1. Activity D
  2. Activity E
  3. Activity F
  4. Activity B
Correct Answer


Project Management- Q5. The role of the project manager relating to integration is MOST appropriately described as:

  1. Ensuring that the stakeholders’ role is integrated with the rest of the team.
  2. Ensuring that management’s role is integrated into the everyday workings of the project.
  3. Ensuring that the various project elements are properly coordinated
  4. Ensuring that team members work together.
Correct Answer


Project Management- Q6. A project manager was involved in preparation of the project charter for an external project. One of the inputs to the project charter was a statement of work (SOW). The SOW may have been received from the customer as part of any of the following except:

  1. As part of a request for information
  2. As part of the business case
  3. As part of a request for proposal
  4. As part of a contract
Correct Answer


Project Management- Q7. You have estimated the cost of your project by calculating the cost of each activity, adding them together to get the cost of a work package, and then you adding together the cost of all work packages. What kind of estimate are you using here?

  1. Top down
  2. Bottom up
  3. Parametric
  4. Ball park estimate
Correct Answer


Project Management- Q8. Which of the following BEST describes why quality is planned in and not inspected in?

  1. It reduces quality and is less expensive.
  2. It improves quality and is more expensive
  3. It reduces quality and is more expensive
  4. It improves quality and is less expensive
Correct Answer


Project Management- Q9. A control chart should always contain:

  1. Upper and lower warning limits
  2. The moving average
  3. Upper and lower control limits
  4. Upper and lower specification limits
Correct Answer


Project Management- Q10. The customer requests a change to the project that would increase the project risk. Which of the following should you do before all the others?

  1. Include the expected monetary value of the risk in the new cost estimate
  2. Talk to the customer about the impact of the change
  3. Analyze the impacts of the change with the team
  4. Change the risk management plan
Correct Answer











User Agreement| |Privacy Policy
© 2026 - Tag&Link – Mostafa Taha Mohamed