Question:

All of the following are examples of the cost of non-conformance EXCEPT:
  1. Scrap
  2. Warranty costs
  3. Rework
  4. Quality training






Q2. Kelly is part of a project management office (PMO). Her office is responsible for the centralized and coordinated management of 18 projects. Each project has its own project manager. Which of the following will not typically be a responsibility of her PMO?

  1. Coaching, mentoring, training, and oversight
  2. Development of a detailed description of each project and the product it produces
  3. Managing shared resources across all the projects administered by the PMO
  4. Developing and managing project policies
Correct Answer

Q3. Agile release planning provides a high-level summary timeline of the release schedule based on the project roadmap. Agile release planning also determines the number of iterations required for the product development. These iterations are also known as:

  1. Epics
  2. Kanbans
  3. Sprints
  4. Phases
Correct Answer

Q4. The project manager’s role during the executing process group of the project can BEST be described as:

  1. A Director
  2. An Integrator
  3. A Coordinator
  4. A Leader
Correct Answer

Q5. A scope change is made on the project. You have determined the effect on the schedule, performed integrated change control, and adjusted the project baselines and the project management plan. What is the NEXT thing to do?

  1. Look for impacts to cost
  2. Notify stakeholders affected by the change.
  3. Submit the change to the change control board for approval
  4. Change the work breakdown structure.
Correct Answer

Q6. The project manager notices that project activities being completed by one department are all taking slightly longer than planned. To date, none of the activities/work packages have been on the critical path, nor have they affected the critical chain planning that has occurred. The project manager is bothered by the problem, since four of the next five critical path activities are being completed by this department. After making three calls, the project manager is finally able to converse with the department manager to determine what is going on. The conversation is slow because both speak different native languages and they are trying to converse in French, a shared language. To make communication easier, the project manager frequently asks the department manager to repeat back what has been said. The department manager communicates that his staff is following a company policy that requires two of the project manager to believe that the policy may include excessive work. This is the fourth time the project manager has heard such a comment. What is the BEST thing to do?

  1. Create a better communications management plan that requires only one language to be the universal language on the project and have translators readily available on a moment’s notice
  2. Contact someone else in the department who speaks the project manager’s native language better to confirm the department manager’s opinion
  3. Find out if the upcoming activities should be re-estimated
  4. Work on increasing the effectiveness of the performing organization by recommending continuous improvement of the policy in question.
Correct Answer

Q7. You are working in a big organization. Due to a change in market conditions your organization needs to raise a small project to accommodate the current change in the organization’s processes. The initiating phase is complete and now you are in the planning phase and developing the project plan. Which of the following project management processes can be omitted for this project?

  1. Perform qualitative risk analysis
  2. Manage quality
  3. Perform quantitative risk analysis
  4. Create WBS
Correct Answer

Q8. Based on the network diagram shown in the chart, what is the duration of the critical path?

  1. 33
  2. 44
  3. 31
  4. 36 73
Correct Answer

Q9. The termination clause and alternative dispute resolution (ADR) mechanism for each procurement in a project is in the:

  1. Scope Statement
  2. Agreement
  3. Resource Calendars
  4. Source Selection Criteria
Correct Answer

Q10. The Project Scope Management Knowledge Area is primarily concerned with:

  1. Defining the scope of work that included in the project
  2. Ensuring that the project includes all the work required, and only the work required, to complete the project
  3. The scope of work required during the initiation phase
  4. Defining the specifications and functionality of the work product
Correct Answer