Question:

You are setting up your project team, and you are looking at a chart that shows that Systems Development will perform programming, Infrastructure Systems will implement the infrastructure, and the Call Center will handle the customer communication. This is an example of what type of chart?
  1. RACI
  2. Organizational Breakdown Structure (OBS)
  3. Work Breakdown Structure
  4. Resource Breakdown Structure (RBS)






Q2. Once the project charter is authorized, it is the project manager’s duty to distribute the charter to all key stakeholders and ensure common understanding of the key deliverables, milestones, and their roles and responsibilities. During which of the following processes is the project charter distributed to the project stakeholders?

  1. Direct and Manage Project Work
  2. Manage Stakeholder Engagement
  3. Develop Project Charter
  4. Manage Communications
Correct Answer

Q3. Quality metrics used during the Control Quality process are defined during which process?

  1. Plan Quality Management
  2. Define Scope
  3. Collect Requirements
  4. Manage Quality
Correct Answer

Q4. A team member in your project is constantly providing incomplete deliverables and not performing well. What should you do first?

  1. Discuss the issue with the team member in private
  2. Discuss the issue with the team member in the presence of the project sponsor
  3. Discuss the issue with the team member in the presence of other team members
  4. Discuss the issue with the team member in the presence of the company's HR manager
Correct Answer

Q5. Seven non-random data points that are still within the upper and lower control limit of a control chart are:

  1. Specification limits
  2. Out of control
  3. In control
  4. Gold plated
Correct Answer

Q6. Identifying ways to eliminate the causes of unsatisfactory performance would MOST likely lead to:

  1. Quality audits
  2. Work performance information
  3. Recommend corrective actions
  4. Updates to the performance measurement baseline.
Correct Answer

Q7. Linear programming is an example of what type of project selection criteria?

  1. Constrained optimization
  2. Comparative approach
  3. Benefit measurement
  4. Impact analysis
Correct Answer

Q8. Different stakeholders might require dissimilar outcomes from a project. An integral component of stakeholder management is managing these competing expectations throughout the project from initiation to closure. Which of the following management techniques can help in this situation?

  1. Stakeholder engagement analysis
  2. Facilitation
  3. Questionnaires
  4. Expert judgment
Correct Answer

Q9. Which of the following is one of the most prominent features of a project following agile approach for product development?

  1. Produce defect-free deliverables
  2. Zero tolerance for rework
  3. Deliver incremental value to the customer
  4. Delivery of the product in a single sprint
Correct Answer

Q10. Which of the Project Schedule Management processes involves identifying and documenting dependencies among schedule activities?

  1. Sequence Activities
  2. Define Activities
  3. Develop Schedule
  4. Control Schedule
Correct Answer