You are working as the project manager on a mega-construction project. You need to prepare a quarterly report for the project investors. You need to collect work performance data and convert that into work performance information. Which of the following processes produces work performance data?
  1. Direct and Manage Project Work
  2. Control Schedule
  3. Control Costs
  4. Manage Communications






Q2. Your company just won a major new project. It will begin in three months and is valued at US $2,000,000. You are the project manager for an existing project. What is the FIRST thing you should do upon hearing of the new project?

  1. Ask management how the new project will use resources
  2. Resource level your project
  3. Crash your project
  4. Ask management how the new project will affect your project.
Correct Answer

Q3. The on-demand scheduling approach used in agile environments is based on the theory-of-constraints and pull-based scheduling concepts from lean manufacturing to limit a team’s work in progress. This is also called:

  1. 5S
  2. Kanban
  3. Andon
  4. Gemba
Correct Answer

Q4. The Cost of Quality principle includes:

  1. The costs of ensuring conformance to requirements
  2. The costs involved when changes are made to the requirements
  3. The cost of deploying a project Configuration Management System
  4. The costs associated with eliminating requirements
Correct Answer

Q5. Which of the following is a tool or technique of the Manage Stakeholder Engagement process?

  1. Communication technology
  2. Communication models
  3. Communication standard
  4. Communication skills
Correct Answer

Q6. A project manager has completed identification of stakeholders and has started planning for a flow instruments installation project in a hospital. While developing the project management plan, a team member states that a stakeholder in the X-ray department is missing from the stakeholder list. Which of the following would be the best response from the project manager?

  1. Authenticate the information from the team member
  2. Include and involve the stakeholder immediately
  3. It is too late to involve a stakeholder in the planning, so ignore the stakeholder
  4. Wait until the execution phase to involve the new stakeholder
Correct Answer

Q7. The project manager is looking at the project’s resource needs and lessons learned from past projects. This information causes the project manager to be concerned about the ability to acquire enough resources from the project in six months. Which of the following would be the LEAST effective preventive action?

  1. Make sure functional managers have a copy of the resource histogram
  2. Show the sponsor the data, and explain the project manager’s concern
  3. Determine metrics to use as an early warning sign that resources will not be available.
  4. Ask functional managers for their opinions.
Correct Answer

Q8. You are performing an audit of one of your project manager’s projects and notice that she did not consider the network diagram as part of the Identify Risks process. As a result, the project manager will probably do which of the following?

  1. Forget some activities in he risk evaluation
  2. Forget activity precedence in her risk evaluation
  3. Forget some path convergence issues in her risk evaluation
  4. Forget some stakeholders in her risk evaluation.
Correct Answer

Q9. During every project team meeting, the project manager asks each team member to describe the work he or she is doing, and the project manager assigns new activities to team members. The length of these meetings has increased because there are many different activities to assign. This could be happening for all of the following reasons EXCEPT:

  1. Lack of a WBS
  2. Lack of a responsibility assignment matrix.
  3. Lack of resource leveling
  4. Lack of team involvement in project planning.
Correct Answer

Q10. Your company requires that before you purchase any routers or switches for the data center you are building, you need to solicit quotes from three separate suppliers prior to submitting the purchase request to the finance department. This policy belongs to:

  1. Organizational Process Assets
  2. Enterprise Environmental Factors
  3. Procurement Management Knowledge Area
  4. Make-or-Buy Decision
Correct Answer