IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Your project is running late and you are over budget. You review the situation and find that it would be difficult for you to complete the project with the given budget. You inform management and they ask you to come up with a new budget. After estimating the new cost, you inform management that you may need 10,000 USD more to complete the project. This is an example of:
  1. Forecast analysis
  2. Status report
  3. Change request
  4. Progress report






Q2. You are a new project manager who has never managed a project before. You have been asked to plan a new project. It would be BEST in this situation to rely on ______ during planning to improve your chance of success.

  1. Your intuition and training
  2. Stakeholder analysis
  3. Historical information
  4. Configuration management
Correct Answer

Q3. Which of the following is not an appropriate method for dealing with a negative risk?

  1. Avoid
  2. Exploit
  3. Transfer
  4. Mitigate
Correct Answer

Q4. Which of the following activities fall under the planning process group but not under project schedule management?

  1. Estimating activity durations
  2. Developing the Schedule Management Plan
  3. Identification of various activities to produce the project deliverables
  4. Developing a detailed description of the project and product being developed
Correct Answer

Q5. The work breakdown structure is created by:

  1. The team
  2. The project manager
  3. Management
  4. The sponsor
Correct Answer

Q6. You have just returned from the weekly change control board meeting at which you presented the requested changes to the employee move project. You had five change requests approved and one request rejected. These are outputs of what process?

  1. Control Quality
  2. Control Scope
  3. Monitor Risks
  4. Perform Integrated Change Control
Correct Answer

Q7. An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. What is the duration of this activity?

  1. 3
  2. 6
  3. 7
  4. 10
Correct Answer

Q8. In which of the following is a scope management plan created?

  1. Validate Scope
  2. Develop Project Management Plan
  3. Define Scope
  4. Create WBS
Correct Answer

Q9. The project manager is working to clearly describe the level of involvement expected from everyone involved in the project in order to prevent rework, conflict, and coordination problems. Which of the following BEST describes the project manager’s efforts?

  1. Develop Project Management Plan and Plan Quality Management
  2. Problem solving, control, and discovering gold plating
  3. Validate Scope and Control Quality
  4. Control Risks, Develop Project Team, and lessons learned
Correct Answer

Q10. You are attending a monthly status meeting with your stakeholders. During the discussion with an influential stakeholder, he asks you about a particular deliverable, He would like to know why it is taking so long to deliver and who is responsible for it. To answer his query, you refer a document and call Tom, who was responsible for this deliverable. What document is this?

  1. Scope statement
  2. Stakeholder register
  3. RACI chart
  4. Issue log
Correct Answer










User Agreement| |Privacy Policy