Question:

Monitoring cost expended to date in order to detect variances from the plan occurs during:
  1. The creation of the cost change control system.
  2. Recommending corrective actions
  3. Updating the cost baseline
  4. Project performance reviews






Q2. What is the primary risk when including reserves, or contingency allowances, in your cost estimate?

  1. Cancelling your project
  2. Understating the cost estimate
  3. Overstating the cost estimate
  4. Tracking the funds
Correct Answer

Q3. All of the following are part of the Perform Quality Control process EXCEPT:

  1. Pareto chart
  2. Control charts
  3. Inspection
  4. Quality audits.
Correct Answer

Q4. To control the schedule, a project manager is reanalyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least amount of flexibility. What technique is being used?

  1. Leads and lags
  2. Work Breakdown Structure
  3. Flowchart
  4. Critical Path Method
Correct Answer

Q5. When writing the roles and responsibilities for team members, you should document the role, authority, responsibility, and competency for each team member. Where must you document this information?

  1. Resource management plan
  2. RACI chart
  3. Resource calendar
  4. Resource Breakdown Structure (RBS)
Correct Answer

Q6. The sponsor has informed you that the resources for your project will be cut. The sponsor wants to know how long the project will take if only nine resources each month are committed to your project. What is this activity called?

  1. Crashing
  2. Floating
  3. Leveling
  4. Fast tracking
Correct Answer

Q7. You have taken over a project from another manager who left the firm. This is a functional organization and the different units are often rather hostile to each other. The project is a large one involving activities that the organization has never done before. You find that the project has what appear to be adequate documentations, including an agreed-to project charter, project management plan, WBS, etc. The project is on schedule and within budget. However, the atmosphere in meetings with the project members often seems tense, and offhand comments made by participants seem to indicate a high level of dissatisfaction with the project. You review all of the major project documents with the key stakeholders and get agreement that they are still accurate, but this does not seem to solve the problem. What is the MOST likely explanation for this situation?

  1. There are personality conflicts amount the project team members that you need to uncover and resolve.
  2. The project does not have an effective sponsor and thus is not viewed as a high priority.
  3. Stakeholders have very different expectations about what the project is supposed to accomplish.
  4. The organizational structure and dynamics prevent people from working together effectively.
Correct Answer

Q8. All of the following are parts of the team’s stakeholder management effort EXCEPT:

  1. Determining stakeholders’ needs.
  2. Identifying stakeholders.
  3. Giving stakeholders extras.
  4. Managing stakeholders’ expectations.
Correct Answer

Q9. Inputs to the Plan Communications Management process include all the following EXCEPT:

  1. Communications requirements.
  2. Stakeholder management strategy.
  3. Company culture.
  4. Forecasts.
Correct Answer

Q10. The BEST description of costs that change with the amount of production is:

  1. Variable costs
  2. Fixed costs
  3. Direct costs
  4. Sunk costs 24
Correct Answer