IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Project Management - Question 1:

Based on the chart, a resource on your project from the consumer affairs department comes to you to tell you that he is taking a two-week leave from work due to a family emergency. He is assigned to activity F, which is currently in progress. This is a problem because activity F has:


Project Management PMP-5135.jpg
  1. One week of float
  2. Two months of float
  3. One month of float
  4. No float






Project Management- Q2. The output of the Validate Scope process is accepted deliverables that are formally signed off by the stakeholders. The stakeholders, on some projects, can get involved with the project as early as:

  1. During the project initiation
  2. During the project planning
  3. During the project execution
  4. During the project monitoring & controlling
Correct Answer


Project Management- Q3. A project manager and his team are using an Ishikawa diagram, trying to determine how various factors might have contributed to project problems. The project manager is involved in which part of the quality management process?

  1. Plan Quality
  2. Utilize Quality tools
  3. Manage Quality
  4. Perform Quality Control
Correct Answer


Project Management- Q4. By policy, the project management office regularly evaluates project performance. This is done in order to ensure standards are being followed. This is an example of:

  1. Plan Quality
  2. Manage Quality
  3. Control Quality
  4. Quality Management
Correct Answer


Project Management- Q5. A project has a payback period of nine months. What does this mean?

  1. It will take the project nine months to start incurring costs
  2. The project will be complete in nine months
  3. The first nine months of the project will provide profit to the company
  4. It will take the project nine months to cover the investment and start generating revenue
Correct Answer


Project Management- Q6. Where should a new project manager look to determine resource requirements?

  1. Resource leveling chart
  2. Resource bar chart
  3. Activity list
  4. Project schedule
Correct Answer


Project Management- Q7. A project charter that formally authorized a project was created. The project charter documented the initial requirements to satisfy stakeholders' needs and expectations. How often should the project charter be revised?

  1. At the beginning, middle, and end of a project
  2. Once a month
  3. Project charter is usually not updated during the course of the project.
  4. As required by the PMO
Correct Answer


Project Management- Q8. Based on the chart, what is the duration of the critical path?

  1. 19
  2. 13
  3. 15
  4. 14
Correct Answer


Project Management- Q9. A scope change is made on the project. You have determined the effect on the schedule, performed integrated change control, and adjusted the project baselines and the project management plan. What is the NEXT thing to do?

  1. Look for impacts to cost
  2. Notify stakeholders affected by the change.
  3. Submit the change to the change control board for approval
  4. Change the work breakdown structure.
Correct Answer


Project Management- Q10. Outputs of the Develop Project Team process are:

  1. Roles and responsibilities, project organization charts, and staffing management plan
  2. Project organization charts, project staff assignments, and roles and responsibilities.
  3. Project manager plan updates, staffing management plan, and project organization charts.
  4. Roles and responsibilities, staffing management plan, and resource availability
Correct Answer











User Agreement| |Privacy Policy
© 2026 - Tag&Link – Mostafa Taha Mohamed