Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You have been assigned as the project manager for a construction project that has had two previous project managers, when you discover that a deliverable will be late. Your analysis shows that the item can be purchased from another seller at a higher price without affecting the schedule. What is the BEST thing to do?
  1. Evaluate the impact of the decision
  2. Discuss the impact with the customer and ask for a decision
  3. Crash or fast track the project.
  4. Change the project management plan to reflect the new due date.






Q2. There are several communication methods used to share and distribute information to stakeholders, team members, and management. Which of the following communication methods is used when you notify the public about environmental effects from your project after implementation by posting reports on the project's website?

  1. Pull communication
  2. Interactive communication
  3. Informal communication
  4. Push communication
Correct Answer

Q3. A new employee of the company is assigned to work on a project that is in the early planning processes. She has to decide if she will accept the assignment to the project or whether she wants to be assigned to a different project. However, the project manager is not at work and is not reachable. Where can the team member look to help her determine what work she is given on the project?

  1. Activity definitions
  2. Project management plan
  3. Job descriptions
  4. Responsibility assignment matrix
Correct Answer

Q4. You are the project manager for a $3,000,000 product development project. Your project is well into the executing process group and remains on time, on budget and no specification. This morning your project sponsor called to express concern about he project. Based on the schedule baseline, the project should be nearing implementation, but the sponsor does not know the current status of the project. You remind the sponsor that your team produces a detailed status report weekly and distributes it via e-mail. The sponsor indicates that e-mail is too impersonal and verbal updates are preferred. This situation suggests problems with which of the follow project management processes?

  1. Plan Communications
  2. Distribute Information
  3. Report Performance
  4. Stakeholders Management
Correct Answer

Q5. You are in the process of dividing work into smaller components so you can get a structured vision of what has to be delivered. What process is this?

  1. Create WBS
  2. Create RBS
  3. Rolling wave planning
  4. Progressive elaboration
Correct Answer

Q6. You are working as a project manager for a high-yield crop development project. Data from the weather agency shows an unfavorable weather pattern for the next few months. As a senior project manager, you want to assess the schedule’s feasibility under adverse conditions and provide some insights to your team. That way, your team can prepare some reserves and plan risk responses if unfavorable conditions exist during execution. Which of the following techniques should you use to simulate risks and other sources of uncertainty to calculate possible schedule outcomes?

  1. Pareto charts
  2. Variance analysis
  3. Crashing
  4. Monte Carlo analysis
Correct Answer

Q7. A software team tracing the root cause of an application failure can use this to help determine the cause(s) of the failure:

  1. Ishikawa diagram
  2. Rummler-Brache swim lane diagram
  3. Threading analysis
  4. Deming chart
Correct Answer

Q8. While visiting the country where a new branch office is being built, you are told that you must pay a US $5,000 fee to the government permit office to obtain the facility permit required by law to start construction. The construction company tells you this is standard practice and is required by law. What should you do?

  1. Pay the fee
  2. Refuse to pay the fee
  3. Have the construction company pay the fee
  4. Have the customer pay the fee
Correct Answer

Q9. When writing the roles and responsibilities for team members, you should document the role, authority, responsibility, and competency for each team member. Where must you document this information?

  1. Resource management plan
  2. RACI chart
  3. Resource calendar
  4. Resource Breakdown Structure (RBS)
Correct Answer

Q10. You are a project manager newly assigned to a large project for your organization. The project charter has been signed, and the stakeholders have been identified. What should you do next?

  1. Ask appropriate team members to submit WBS input
  2. Initiate the scope planning process
  3. Start the develop project management plan process
  4. Begin the activity definition process
Correct Answer