Question:

The acceptable range of variation of a process is the ________ on a control chart.
  1. Mean
  2. Specification limit
  3. Rule of seven
  4. Upper and lower control limit.






Q2. You are managing an electronic chip design project for a customer. There are a number of engineers and subject matter experts from the customer’s organization that have been assigned as resources to the project plus several additional design engineers that your company has supplied. All the engineers were involved in the development of a prototype chip, an extremely time-consuming and expensive process. Upon the completion of the prototype, you submit it for review to ensure there are no patent infringement issues with the design. However, the review determines there are several issues that could result in an intellectual property dispute with the patent owners should the prototype design be released commercially. Resources from your company developed the affected prototype elements, as well as from your customer’s organization. What should you do?

  1. Ask the engineers to revise the design and resubmit it
  2. Notify the project stakeholders immediately
  3. Request permission to use the copyright material
  4. Submit the prototype as is since the budget and schedule do not accommodate rework
Correct Answer

Q3. Breaking down project activities into smaller components in order to obtain a more accurate cost estimate and then aggregating the estimates of the lower-level components is:

  1. Work breakdown structure
  2. Analogous estimating
  3. Decomposition
  4. Bottom-up estimating
Correct Answer

Q4. The project has been going well, except for the number of changes being. The project is being installed into even different department within the company and will greatly improve departmental performance when operational. There are 14 project management processes selected for use on this project. The project manager is a technical expert as well as having been trained in communications and managing people. Which of the following is the MOST likely cause of the project problems?

  1. The project manager was not trained in understanding the company environment.
  2. The project should have more management oversight since it will result in such great benefits to the company.
  3. The project should have used more of the project management processes.
  4. Some stakeholders were not identified
Correct Answer

Q5. A document provides detailed deliverables, activities, and scheduling information about components. Other information includes the code of account identifier, assumptions and constraints, schedule milestones, resources required, and acceptance criteria. This document can possibly be:

  1. WBS dictionary
  2. Scope statement
  3. WBS
  4. Statement of work
Correct Answer

Q6. Your cost forecast shows that you will have a cost overrun at the end of the project. Which of the following should you do?

  1. Eliminate risks in estimates and re-estimate.
  2. Meet with the sponsor to find out what work can be done sooner.
  3. Cut quality.
  4. Decrease scope.
Correct Answer

Q7. Project managers need to be aware of Student Syndrome, also known as procrastination, which means that people start to apply themselves only at the last possible moment before the deadline. This concept is similar to Parkinson’s Law which states that:

  1. Work only gets completed during the second half of the allocated time.
  2. Work never gets completed on time even if sufficient time has been allocated.
  3. Work expands to fill the time available for its completion.
  4. Effort expands to fill the time available for the completion of a work package.
Correct Answer

Q8. You are beginning a new project that has been attempted, but unsuccessfully, several times in the past few years. Previous projects were cancelled because e of “politics” (differing views and direction by key stakeholders on the project). This is an example of:

  1. Stakeholder analysis.
  2. Scope management.
  3. Historical information.
  4. Risk identification
Correct Answer

Q9. What is the primary risk when including reserves, or contingency allowances, in your cost estimate?

  1. Cancelling your project
  2. Understating the cost estimate
  3. Overstating the cost estimate
  4. Tracking the funds
Correct Answer

Q10. A team member complains to the project manager that another team member has once again failed to provide necessary information. The project manager meets with both team members to uncover the reason for the problem. This is an example of:

  1. Withdrawal
  2. Confronting
  3. Compromising
  4. Smoothing.
Correct Answer