IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A seller is awarded a contract to build a pipeline. The contract terms and conditions require a work plan be issued for the buyer’s approval prior to commencing work, but the seller fails to provide one. Which of the following is the BEST thing for the buyer’s project manager to do?
  1. File a letter of intent
  2. Develop the work plan, and issue it to the seller to move things along
  3. Issue a default letter
  4. Issue a stop order to the seller until a work plan is prepared.






Q2. The project management team performed activities such as measuring, examining, and verifying to determine whether work and deliverables met requirements and product acceptance criteria. Which of the following choices refers to a different set of activities than the ones just mentioned?

  1. Walkthroughs
  2. Prevention
  3. Inspection
  4. Reviews
Correct Answer

Q3. Which motivational theory says that working conditions, salary, and relationships at work do NOT improve motivation?

  1. Maslow
  2. Deming
  3. McGregor
  4. Herzberg
Correct Answer

Q4. There is a serious defect in the finished product of a project that was completed a few months ago, resulting in a recall campaign to recall the defective products. What would be the best classification for these types of costs?

  1. To complete performance index (TCP)
  2. Cost variance
  3. Cost of conformance
  4. Cost of nonconformance
Correct Answer

Q5. The primary customer of a project has requested an application change during user testing. As project manager, how should you BEST address this issue?

  1. Develop a risk mitigation plan
  2. Through a formal change request
  3. Inform the project sponsor of changes to the scope cost and schedule
  4. Ensure that scope change complies with all relevant contractual provisions
Correct Answer

Q6. You are working in a big organization. Due to a change in market conditions your organization needs to raise a small project to accommodate the current change in the organization’s processes. The initiating phase is complete and now you are in the planning phase and developing the project plan. Which of the following project management processes can be omitted for this project?

  1. Perform qualitative risk analysis
  2. Manage quality
  3. Perform quantitative risk analysis
  4. Create WBS
Correct Answer

Q7. You are in the middle of a new product development project for your publicly traded company when you discover that the previous project manager made a $3,000,000 payment that was not approved in accordance with your company policies. Luckily, the project cost performance index (CPI) is 1.2. What should you do?

  1. Put the payment in an escrow account.
  2. Bury the cost in the largest cost center available.
  3. Ignore the payment
  4. Contact your manager
Correct Answer

Q8. You are working on a project which is under budget and ahead of schedule. The project is 85% complete, and the client comes and asks you to terminate the project because he fears a possible regulation can impact his project. You review the project parameters and find that you can complete the project before the proposed legislation comes into existence; moreover, you won’t need any extra funding. What will your next steps be?

  1. Tell the client about your findings and ask him to reconsider his decision
  2. Initiate the close project process
  3. Immediately release your team members
  4. Convince your management to discuss the issue with the client
Correct Answer

Q9. You are working on a medium-sized project and management has decided to forego the perform quantitative risk analysis process. So, after identifying risks, you start the qualitative risk analysis process and now you are going to prioritize them. Which of the following techniques are you going to use?

  1. Probability and impact
  2. Fishbone diagram
  3. Scatter diagram
  4. Sensitive analysis
Correct Answer

Q10. Using the chart, a new activity, (R) with the duration of 5 is added to this project. Activity R has a predecessor as activity A, and a successor as activity B. How long will the project now take?

  1. 49
  2. 48
  3. 38
  4. 52
Correct Answer










User Agreement| |Privacy Policy