IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

The project management team performed activities such as measuring, examining, and verifying to determine whether work and deliverables met requirements and product acceptance criteria. Which of the following choices refers to a different set of activities than the ones just mentioned?
  1. Walkthroughs
  2. Prevention
  3. Inspection
  4. Reviews






Q2. Which of the following statements is incorrect?

  1. Developing a project team is the responsibility of the project manager.
  2. A project manager must not acquire resources needed to develop effective project teams.
  3. High team performance can be achieved using open and effective communications.
  4. Teamwork is a critical success factor for a project.
Correct Answer

Q3. You have two activities with Finish to Start sequences. The duration of the first activity is 10 days, and the duration of the second activity is 8 days. The estimated time completed for these activities is 18 days. The client asks you complete these activities within 15 days; you review his request and agree to do so at no extra cost. Now, you plan to start the second activity three days before the first activity completes so that both activities can be completed in 15 days. This process is known as:

  1. Schedule modification
  2. Fast tracking
  3. Crashing
  4. None of the above
Correct Answer

Q4. During the team member acquiring process, you observe that a particular employee from another department can be used for your project for some work. Therefore, you ask their functional manager to provide the employee on alternate days. The functional manager says they can provide you with the particular employee for only two days a week. Which technique are you using here?

  1. Acquire project team
  2. Negotiation
  3. Pre-assignment
  4. Develop project team
Correct Answer

Q5. A small project with a limited budget is trying to curtail costs. Which of the following processes may be eliminated in such a project?

  1. Perform Qualitative Risk Analysis
  2. Perform Quantitative Risk Analysis
  3. Identify Risks
  4. Plan Risk Management
Correct Answer

Q6. Although it is highly recommended that lessons learned are captured and documented throughout the project lifecycle, lessons learned are finalized during project closure. At this stage, responses to high-level questions may be gathered and documented. Which of the following is not an appropriate question to ask at this stage?

  1. What were the top significant project successes?
  2. How relevant the historic lessons learned were to this project during execution?
  3. What obstacles or unanticipated circumstances made it difficult to complete the project?
  4. What should have been done differently in this project?
Correct Answer

Q7. When should a schedule baseline be created and used?

  1. At the beginning of the project and used to compare schedule performance on status reports
  2. At the end of the project and then used to measure team performance
  3. At the end of the project and included in the archive
  4. At the beginning of the project and used during the project to measure performance
Correct Answer

Q8. During a work breakdown structure meeting, you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want to decompose the work packages to assist you in estimating, executing, and controlling the project. These decomposed work packages are:

  1. Work packages can't be decomposed into smaller units
  2. Activities
  3. Milestones
  4. Control Accounts
Correct Answer

Q9. When are risk identification activities performed?

  1. During the Perform Qualitative Risk Analysis process
  2. During the Plan Risk Management process
  3. During the Perform Quantitative Risk Analysis process
  4. Ongoing throughout the project
Correct Answer

Q10. Based on the chart, what is the duration of a critical path?

  1. 30
  2. 23
  3. 49
  4. 46
Correct Answer










User Agreement| |Privacy Policy