Which of the following is not an activity related to the Direct and Manage Project Work process?
  1. Inspecting the project deliverables for completeness
  2. Implementing approved changes
  3. Creating project deliverables to meet the planned project work
  4. Performing activities to accomplish project objectives






Q2. Adam has just taken over a construction project. The project is currently in the planning phase of the project lifecycle. Adam’s next deliverable is to produce an effective stakeholder engagement strategy. Which of the following is the most important component of an effective stakeholder engagement plan?

  1. Management style
  2. Risk tolerance
  3. Construction know-how
  4. Communications
Correct Answer

Q3. During the completion of the project work, a project manager wants to ensure that the quality of the end product is acceptable. The BEST way to do this is by:

  1. Checking quality against the standards set in the quality management plan
  2. Identifying the quality standards you want the end product to meet
  3. Performing cost-benefit analysis
  4. Determining the cause of a problem using a fishbone diagram.
Correct Answer

Q4. Probabilistic analysis o the project and probability of achieving the project cost are completed during:

  1. Identify Risks
  2. Perform Qualitative Risk Analysis
  3. Perform Quantitative Risk Analysis
  4. Plan Risk Responses.
Correct Answer

Q5. A project manager receives a deliverable from one of the team members to provide to the customer. While looking at the deliverable, the project manager notes that the document is smaller than what he expected and does not contain what he thought it should. The project manager should FIRST:

  1. Discuss it with the team member
  2. Contact the team member’s manager to get that person additional training
  3. Audit the development process
  4. Complete scope validation
Correct Answer

Q6. You are managing a project where your team is physically located with client personnel at a remote location. There is a high level of interaction between your team and client personnel, and client satisfaction is considered very important. Since the client is expressing a very high level of satisfaction with the project’s progress, your management has indicated no concerns about the project. However, you are behind schedule and over budget. In addition, morale among team members is low, and several team members have talked about quitting. Team members complain regularly about priority adjustments and alteration of activities. The weekly reports you receive about activities completed are often difficult to relate to the WBS and the project management plan. What action should you take to MOST effectively address these problems?

  1. You should enforce scope control.
  2. You should identify ways to make team members’ work more satisfying using the most applicable motivational theory.
  3. You should incur the extra expenses necessary to be on-site to more closely monitor the activities of the project team.
  4. You should create a reward and punishment system to ensure that project team members complete activities within the timeframes outlined in the project management plan.
Correct Answer

Q7. During the Define Activities process, the team discovers that they do not know enough to define the activities for 30 percent of the work packages. What would be the BEST course of action?

  1. Redo the Define Scope process
  2. Review the project charter with the sponsor and the team
  3. Continue on to Sequence Activities process and define the activities at a later date.
  4. Include this problem as a part of risk identification
Correct Answer

Q8. Which of the following may help in ensuring that certain bidders in the procurement process do not receive preferential treatment and that all prospective sellers have a clear and common understanding of the procurement?

  1. Use of weighted criteria
  2. Use of screening techniques
  3. Use of bidder conferences
  4. Use of expert judgment
Correct Answer

Q9. Earned value measurement is an example of:

  1. Performance reporting
  2. Planning control
  3. Ishikawa diagrams
  4. Integrating the project components into a whole.
Correct Answer

Q10. The Verify Scope process is different than the Perform Quality Control process in that:

  1. Perform Quality Control focuses on the quality of the project, while Verify Scope focuses on customer acceptance
  2. Verify Scope is performed throughout the project and Perform Quality Control is done throughout the project.
  3. Perform Quality Control is considered part of Plan Quality while Verify Scope is not.
  4. Scope verification is provided to the project management team while quality control is provided to the project.
Correct Answer