IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

John, a project manager for Code Crashers, Inc., has a project with a group of inexperienced programmers that will develop a software package that creates Material Safety Data Sheets (MSDS) for a chemical company. This situation strongly resembles a project his colleague, Peter, worked on in 2006. If John needs to come up with a rough order of magnitude estimate, what tool or technique should he use?
  1. Parametric Estimating
  2. Bottom Up Estimating
  3. Three-point estimate
  4. Analogous Estimating






Q2. Which of the following is an output of the Define Activities process?

  1. A WBS
  2. An activity list
  3. A network diagram
  4. A project schedule
Correct Answer

Q3. Which of the following is the correct logical sequence of the five process groups?

  1. Planning, Monitoring and Controlling, Initiating, Executing, Closing
  2. Planning, Initiating, Executing, Monitoring and Controlling, Closing
  3. Initiating, Monitoring and Controlling, Planning, Executing, Closing
  4. Initiating, Planning, Executing, Monitoring and Controlling, Closing
Correct Answer

Q4. The customer starts to have cash flow problems, because other projects are being completed early. The customer notifies the project manager that there will be limits on when funds will be available for the project. The project CPI is currently 1.02, and the estimate to complete is US $927,000. If the project manager performs funding limit reconciliation, there will also MOST likely be a change to the:

  1. Resource assigned.
  2. Number of change requests
  3. Cost baseline
  4. Project schedule 21
Correct Answer

Q5. You are in the middle of a major new facility construction project. The structural steel is in place and the heating conduits are going into place when a senior manager informs you that he is worried that the project will not meet the quality standards. What should you do in this situation?

  1. Assure senior management that during the Plan Quality process it was determined that the project would meet the quality standards
  2. Analogously estimate future results.
  3. Form a quality assurance team
  4. Check the results from the last quality management plan.
Correct Answer

Q6. You are the Project Manager for JT's Lumber Yard. You are trying to forecast estimates for the final phase of the project you are currently working on. Based on the performance of the project to date, which formula can be used to estimate the total value of the project when completed, assuming similar variances will not occur?

  1. ETC = (BAC - EV)/CPI
  2. SV = EV - PV
  3. CPI = EV/AC
  4. EAC = AC + BAC - EV
Correct Answer

Q7. You are the project level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem?

  1. Quality audits
  2. Risk quantification reports
  3. Regression analysis
  4. Monte Carlo analysis
Correct Answer

Q8. All of the questions are common outputs of risk management EXCEPT:

  1. Contract terms and conditions
  2. A risk response plan
  3. Schedule reserves
  4. An approved project management plan.
Correct Answer

Q9. The purpose of lessons learned is to bring together any insights gained during a project that can be usefully applied on future projects. When should a project manager ideally commence this activity?

  1. At the start of project planning
  2. At the start of project execution
  3. During the project closure
  4. From project kickoff meeting
Correct Answer

Q10. Julia is managing a complex industrial process reengineering project. She has identified all her key project stakeholders and has conducted individual interviews with them to identify other project stakeholders, as well. However, Julia is still not satisfied with her project’s stakeholders list; she believes there may be more key external stakeholders missing from the list. What can help Julia in this situation?

  1. Use stakeholder register templates from the organizational process assets
  2. Conduct more meetings with the key stakeholders
  3. Get over her fear and finalize the project stakeholder register
  4. Seek expert judgment from subject matter experts
Correct Answer










User Agreement| |Privacy Policy