IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Which of the following is incorrect regarding a bidders conference?
  1. Questions from each seller should be handled confidentially and not shared with other sellers.
  2. No bidders should receive preferential treatment, even if they are part of the company's existing list of approved suppliers.
  3. Bidder conferences should not involve individual face-to-face meetings.
  4. All prospective sellers should be allowed to have a common understanding of the procurement.






Q2. For projects where a business analyst collaborates with the project managers in managing the project scope, which of the following task is most likely to be performed by the business analyst?

  1. Acquire project resources
  2. Monitor the change control process
  3. Elicit, document, and manage stakeholder requirements
  4. Control project costs
Correct Answer

Q3. You have a project with four activities as follows. Activity 1 can start immediately and has an estimated duration of 1. Activity 2 can start after activity 1 is completed and has an estimated duration of four. Activity 3 can start after activity 2 is completed and has an estimated duration of five. Activity 4 has an estimated duration of 8. It can start after activity 1 is completed. Both activity 3 and 4 must be completed before the project is complete. What is the critical path of the project?

  1. Start, 1, 2, 3, End
  2. Start 1, 4, 3, End
  3. Start 1, 4, End
  4. Start 1, 2, 3, 4, End Activity Baseline Crash Time Cost Time Cost A 10 $4,000 8 $6,000 B 2 $6,000 2 $6,000 C 14 $22,000 12 $26,000 D 6 $9,000 5 $10,000 E 9 $14,000 7 $19,000 F 8 $18,000 4 $36,000 76
Correct Answer

Q4. You are a consulting project manager and an investment bank has a contract with you to run a large information technology project that is expected to last 15 months. During the Direct and Manage Project Work process, you discover that several regulatory requirements were addressed in the project management plan but missed from the scope statement. Failure to meet these requirements could result in legal action against the company. However, implementing the technology to comply with these regulations could exceed the budget and scope of the project and result in the cancellation of the project. What should you do?

  1. Do not do anything as these requirements are not a part of the scope baseline.
  2. Request additional funds to implement these requirements.
  3. Submit a change request to incorporate the missed requirements in the project's scope.
  4. This is a classic example of scope creep and such requirements must be ignored.
Correct Answer

Q5. Under which circumstances is it BEST to use a network diagram rather than a bar chart?

  1. To report to the sponsor
  2. To show interdependence between activities
  3. To track progress or to report to the team
  4. To create a work breakdown structure
Correct Answer

Q6. You are reviewing an old project file where you find a document which contains the project description, important requirements, milestones, and project budget. What document is it?

  1. Scope statement
  2. Project charter
  3. Scope baseline
  4. Procurement document
Correct Answer

Q7. The Code of Ethics and Professional Conduct has as its foundation four values identified by practitioners from the global project management community. They are:

  1. Respect, fairness, transparency, and freedom
  2. Responsibility, transparency, fairness, and honesty
  3. Respect, freedom, honesty, and transparency
  4. Responsibility, respect, fairness, and honesty
Correct Answer

Q8. During the development of the project stakeholder engagement plan, a project manager is usually dependent on the voice of the project stakeholders to obtain expert opinion. Which of the following is an important tool available to the project manager for gathering and organizing stakeholders’ information?

  1. Fishbone diagrams
  2. Control charts
  3. Histograms
  4. Focus groups
Correct Answer

Q9. A dependency requiring that design be completed before manufacturing can start is an example of:

  1. Discretionary dependency
  2. External dependency
  3. Mandatory dependency
  4. Scope dependency
Correct Answer

Q10. Rina and Gimo are the senior developers in a website development project. They have argued about the best web design product to use in developing the new website. As the project manager, you use a forcing approach to make a decision and reduce the conflict. What is the main characteristic of this approach?

  1. Forcing to close the project
  2. Highlighting areas of agreement rather than areas of disagreement
  3. Asserting one‘s viewpoint at the expense of others
  4. Withdrawing from the actual conflict
Correct Answer










User Agreement| |Privacy Policy