IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

The Code of Ethics and Professional Conduct has as its foundation four values identified by practitioners from the global project management community. They are:
  1. Respect, fairness, transparency, and freedom
  2. Responsibility, transparency, fairness, and honesty
  3. Respect, freedom, honesty, and transparency
  4. Responsibility, respect, fairness, and honesty






Q2. During project planning, you estimate the time needed for each activity and then add the estimates to create the project estimate. You commit to completing the project by this date. What is wrong with this scenario?

  1. The team did not create the estimate and estimating takes too long using that method
  2. The team did not create the estimate and a network diagram was not used.
  3. The estimate is too long and should be created by management
  4. The project estimate should be the same as the customer’s required completion date
Correct Answer

Q3. You have just completed a solid waste management project in an underdeveloped country. The contractor you are working for has a strict policy of abiding by local laws and rules although the local resources working on the project have a much more lax approach to following laws and policies. Now at the end of the project, you are handing over the operational equipment to the local operators and disposing of the leftover inventory and other materials that were used during the project. More than 50 percent of the toxic materials used during the project remains in your inventory. There is no law that would prohibit you from disposing of either the type or quantity of remaining materials in the local sewage system. What should you do?

  1. Give the material to local resources to dispose of by selling it to a recycling facility
  2. Do not dispose of the materials improperly
  3. Dispose of the material in the local sewage system; there is no law applicable here
  4. Abandon the materials in the project facility you are handing over to the local operators
Correct Answer

Q4. You take over a project hat is US $100,000 over budget. You know that he team has completed US $500,000 worth of work. Your sponsor has been calling all day leaving messages while you were in meetings asking for a quick update on the project status. What will you tell him when you return his call?

  1. The CPI is 0.90
  2. The SPI is 1.10
  3. The CPI is 0.83
  4. The SPI is 0.83 33
Correct Answer

Q5. To help the project team function more efficiently on complex and interrelated activities, the project manager decides to use a war room. What does this mean?

  1. All the project records are kept in many locations
  2. The tools needed to accomplish the work are kept in one place with easy access by the team from various locations.
  3. The entire team is located in one area.
  4. The project’s entire senior management team is located in one area.
Correct Answer

Q6. The project manager of a large construction project is responsible for ensuring that all changes to the building plans are approved and tracked before they are implemented. These activities form part of which process?

  1. Validate Scope
  2. Perform Configuration Management
  3. Perform Integrated change control
  4. Control Quality
Correct Answer

Q7. A project manager would like to resolve conflicts by a give-and-take attitude rather than by a one-sided approach. Which of these approaches is he likely to use?

  1. Forcing
  2. Problem-solving
  3. Directing
  4. Withdrawing
Correct Answer

Q8. You have completed a milestone in your software development project, and you are now verifying that the product meets the specifications outlined in the project management plan. In which process group is this process?

  1. Closing
  2. Monitor and Controlling
  3. Executing
  4. Planning
Correct Answer

Q9. Your project team members have just started to work together and are now adjusting their work habits and behaviors to support each other. Which stage of the Tuckman ladder has your team just entered?

  1. Norming
  2. Performing
  3. Forming
  4. Storming
Correct Answer

Q10. A project manager is estimating the project duration and finds that the only information available to him is a previous project that was quite different from the current one. However, some portions of the previous project were similar to the current one. Which of the following tools is the project manager likely to use to compare current project's activity durations with the similar previous activities?

  1. Analogous estimating
  2. Program Evaluation and Review Technique (PERT)
  3. Three-point estimates
  4. Parametric estimating
Correct Answer










User Agreement| |Privacy Policy