Question:

During the Control Scope process, analysis of the scope performance resulted in a change request to the scope baseline. This change request will be processed for review and disposition in the:
  1. Control Quality
  2. Perform Integrated Change Control
  3. Monitor and Control Project Work
  4. Validate Scope






Q2. Which of the following approaches can assist in managing ambiguity risks?

  1. Monte Carlo analysis
  2. Root cause analysis
  3. Seeking expert external input
  4. Conducting sprint retrospectives
Correct Answer

Q3. At a critical design review meeting for a large project, several important issues surfaced. After hearing about a major technical problem, one of the subcontractor’s engineers mentions that he experienced a similar situation on another project, he has some ideas on how to solve the current problem. What type of power is the engineer using?

  1. Manipulative
  2. Formal
  3. Expert
  4. Referent.
Correct Answer

Q4. Based on the chart, what is the duration of a critical path?

  1. 30
  2. 23
  3. 49
  4. 46
Correct Answer

Q5. While conducting interviews for a project manager position, you notice that your classmate is one of the prospective candidates. What should you do immediately?

  1. Encourage your classmate by offering some tips
  2. Resign from the interview panel
  3. Remove your classmate from the list
  4. Inform the interview panel of the relationship
Correct Answer

Q6. As project manager, you scheduled a status update meeting. During the meeting, a problem developed, and the group discussed it. The day after the meeting, Kevin approached you and expressed his concern that the problem was not truly resolved. After thinking about it, he felt that his concerns were still valid and should be addressed. What conflict resolution method was likely used at the status meeting?

  1. Smoothing
  2. Forcing
  3. Withdrawal
  4. Collaboration
Correct Answer

Q7. You have a project in which you are responsible for building a condo complex in a resort town. The project is expected to take two years to complete. During your work breakdown structure meeting, you have decomposed many deliverables into work packages and schedule activities. However, there are some work packages that will occur a year from now, so you have elected not to decompose those deliverables and work packages at this time. This is an example of what tool or technique?

  1. Scope Creep
  2. Poor Planning
  3. Rolling Wave Planning
  4. Time-delayed Decomposition
Correct Answer

Q8. The project manager is working to clearly describe the level of involvement expected from everyone involved in the project in order to prevent rework, conflict, and coordination problems. Which of the following BEST describes the project manager’s efforts?

  1. Develop Project Management Plan and Plan Quality Management
  2. Problem solving, control, and discovering gold plating
  3. Validate Scope and Control Quality
  4. Control Risks, Develop Project Team, and lessons learned
Correct Answer

Q9. All of the following are outputs of the Create WBS process EXCEPT:

  1. Scope baseline
  2. Change requests
  3. WBS dictionary
  4. Updates to the requirements documentation
Correct Answer

Q10. An experienced project manager was assigned a project of small scope. Which of the following could be true of the project?

  1. Defining Activities, sequencing activities, estimating activity durations, and developing the schedule could be viewed as a single process.
  2. Estimating activity durations may be skipped for the project.
  3. Developing and Controlling the schedule could be viewed as a single process.
  4. Defining Activities, estimating activity durations, developing the schedule, and controlling the schedule could be viewed as a single process.
Correct Answer