A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as activity C is completed. Activity E must be completed before activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. What is the critical path?
  1. Start A, C, F, End
  2. Start B, C, E, G, End
  3. Start D, E, G, End
  4. Both Start –B—C—E—G—End and Start –D—E—G—End






Q2. Determining the physical resources, quantities of each, and when they would be used is the process of:

  1. Resource selection
  2. Estimate Activity Resources
  3. Resource leveling
  4. Define Activities
Correct Answer

Q3. Which of the following is not a PMBOK Knowledge Area?

  1. Procurement management
  2. Integration management
  3. Execution management
  4. Communications management
Correct Answer

Q4. In addition to a project management plan, the project team must create plans for each component of the project. These plans are called:

  1. Sub-plans
  2. Process plans
  3. Component plans
  4. Management plans
Correct Answer

Q5. Gene is the project manager of a large highway expansion project. He has a number of stakeholders with competing priorities and agendas, and he often has to resolve conflicts among stakeholders. Which knowledge area manages communications with the project stakeholders?

  1. Project Quality Management
  2. Project Stakeholder Management
  3. Project Communications Management
  4. Project Resource Management
Correct Answer

Q6. During which project management process group are budget forecasts created?

  1. Monitoring and controlling
  2. Planning
  3. Initiating
  4. Executing
Correct Answer

Q7. After one year of construction, an office building is scheduled for completion on 30 January. The landscaping work needs to start 15 days prior to the building’s completion. Which of the following relationships most likely represents the relationship of the start of landscaping work to the completion of the office building?

  1. Finish-to-start with a 15-day lead
  2. Start-to-finish with a 15-day lead
  3. Finish-to-start with a 15-day lag
  4. Start-to-finish with a 15-day lag
Correct Answer

Q8. While conducting interviews for a project manager position, you notice that your classmate is one of the prospective candidates. What should you do immediately?

  1. Encourage your classmate by offering some tips
  2. Resign from the interview panel
  3. Remove your classmate from the list
  4. Inform the interview panel of the relationship
Correct Answer

Q9. The most detailed level of the WBS is the _______________ .

  1. Control Account
  2. Work package
  3. Scope statement
  4. Accepted Deliverable
Correct Answer

Q10. The purpose of a fishbone diagram is to:

  1. Explore past outcomes and apply then to the current project.
  2. Stimulate thinking, organize thoughts and generate discussion.
  3. Determine the organization of the project.
  4. Show functional responsibilities and how they are related to one another and to the objectives of the project.