Question:

You are in the middle of project executing and find that you are running out of money due to unanticipated changes. What is the BEST thing to do?
  1. Crash or fast track the project
  2. Ask for a change to the project budget
  3. Use resources that do not change against the project
  4. Re-evaluate the risk analysis and contingency funding






Q2. A particular stakeholder has a reputation for requesting many changes on projects. What is the BEST approach a project manager can take at the beginning of the project to manage this situation?

  1. Say "No" to the stakeholder a few times to dissuade him from submitting more changes.
  2. Get the stakeholder involved in the project as early as possible.
  3. Talk to the stakeholder's boss to find ways of directing the stakeholder's activities to another project.
  4. Ask that the stakeholder not be included in the stakeholder listing.
Correct Answer

Q3. A team member in your project is constantly providing incomplete deliverables and not performing well. What should you do first?

  1. Discuss the issue with the team member in private
  2. Discuss the issue with the team member in the presence of the project sponsor
  3. Discuss the issue with the team member in the presence of other team members
  4. Discuss the issue with the team member in the presence of the company's HR manager
Correct Answer

Q4. All of the following are outputs of the Monitor and Control Project Work process EXCEPT:

  1. Rejected change requests
  2. Recommend corrective actions
  3. Forecasts
  4. Recommend defect repair
Correct Answer

Q5. An employee approaches you and asks to tell you something in confidence. He advises you that he has been performing illegal activities within the company for the last year. He is feeling guilty about it and is telling you in order to receive advice as to what he should do. What should you do?

  1. Ask for full details.
  2. Confirm that the activity is really illegal.
  3. Inform your manager of the illegal activity.
  4. Tell the employee to inform his boss.
Correct Answer

Q6. Originally, your project had give team members. Now the scope has expanded, and there are total of eight people on the project team. How many communication channels have been added?

  1. 9
  2. 10
  3. 18
  4. 28
Correct Answer

Q7. You have advertised in several newspapers to inform interested contractors to apply for a bid for some of your procurement needs. Which process are you currently in?

  1. Plan procurement management
  2. Conduct procurement
  3. Control procurement
  4. None of the above
Correct Answer

Q8. Your project team has identified a major project risk. After talking to the project management office, they determine that a reserve on the project is not necessary. What is the NEXT step?

  1. List the time or cost overrun expected on the project in your project management plan.
  2. Develop risk transference strategies.
  3. Create a risk response plan that includes the risk.
  4. Ignore he risk until it happens.
Correct Answer

Q9. A project manager is starting work on a complex project. There will be people from two different countries involved. The project sponsor is from a third country, and the work is being done on an expedited schedule in your country with 14 electrical engineers, 4 architects and their staffs, 3 mechanical engineers, and 2 maintenance experts. What should the project manager do to make sure all the work in this project is identified?

  1. Create a clear management plan, and put it in writing.
  2. Create a WBS with input from all parties involved.
  3. Identify the laws of each country involved.
  4. Create a scope control system.
Correct Answer

Q10. Resource requirements are determined:

  1. Before the project schedule and after the network diagram
  2. After the project schedule and project scope statement
  3. After the project schedule and WBS
  4. Before the project scope statement and the network diagram 43
Correct Answer