IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You work as an engineer for a large engineering firm. During this past week, you have corresponded with your department supervisor about the horizontal stabilizers required for the wings on a new aircraft you are designing. Which communication dimension does this represent?
  1. Horizontal
  2. Formal
  3. External
  4. Upward






Q2. You are in the execution stage of your project, and you are informed that “corporate” will send in a team of consultants to review whether your project activities comply with your company’s and PMI’s policies, standards, and procedures. This is an example of:

  1. Quality Audit
  2. Organizational Process Assets
  3. Process Analysis
  4. Recommended Corrective Actions
Correct Answer

Q3. A key project in an organization has been ignored, due to high travel expenses associated with the movement of subject matter experts and other specialists across various project locations. Which of the following might allow such a project to be undertaken in a cost-efficient manner?

  1. Management sign-off
  2. Negotiation
  3. Virtual teams
  4. Co-location
Correct Answer

Q4. An estimate that is +/-50 percent of actual is considered a:

  1. Budget estimate
  2. Rough order of magnitude estimate
  3. Definitive estimate
  4. Parametric estimate.
Correct Answer

Q5. While planning the project, you discover that an expert resource might be available to work on you project. However, the resource manager will not commit to the resource being on your team at the present time. The BEST thing to do would be to estimate the activity:

  1. As if the expert resources were available.
  2. As though you had an average resource doing the activity.
  3. As if you had an inexperienced resource
  4. Using the Delphi technique.
Correct Answer

Q6. You are in the identifying risks process. You are meeting with your team members and stated that the project may be delayed because of the late delivery of certain consumables for your project. Now you ask the team members to find ways in which this problem can occur. What technique are you using here?

  1. Assumption and constraint analysis
  2. Brainstorming
  3. Sensitivity analysis
  4. Root cause analysis
Correct Answer

Q7. The key objective of stakeholder management is:

  1. Communication.
  2. Coordination.
  3. Satisfaction.
  4. Relationships.
Correct Answer

Q8. Payment for routine government action by a foreign official is:

  1. A bribe
  2. Allowed
  3. Not payable upon violation of government law
  4. Allowed only if they process the project schedule
Correct Answer

Q9. The communications management plan is developed to meet the needs of the:

  1. Project sponsor
  2. Team
  3. Project manager
  4. Stakeholders.
Correct Answer

Q10. You are sitting with your team members and experts in a room and defining the definition of probability of events occurring and the impact. What process is this?

  1. Identify risks
  2. Perform qualitative risk analysis
  3. Plan risk management
  4. Plan risk responses
Correct Answer










User Agreement| |Privacy Policy