Question:

An estimate that is +/-50 percent of actual is considered a:
  1. Budget estimate
  2. Rough order of magnitude estimate
  3. Definitive estimate
  4. Parametric estimate.






Q2. Which of these is not an established Estimate Activity Durations technique?

  1. Three Point Estimating
  2. Parametric Estimating
  3. Analogous Estimating
  4. Critical Path Estimation
Correct Answer

Q3. Change requests are an output of which processes?

  1. Manage Project Team and Report Performance
  2. Manage Stakeholder Expectation and Determine Budget
  3. Define Scope and Plan Communications
  4. Plan Procurements and Perform Qualitative Risk Analysis.
Correct Answer

Q4. Diana is managing the development of a mobile phone application. Half the project work has been completed. Diana is currently reviewing her stakeholder engagement plan. She finds that some of the resisting stakeholders have now become supportive. How should Diana update her stakeholder engagement plan?

  1. Do not update the stakeholder engagement plan at this stage since things are getting better.
  2. Transfer these stakeholders to the project supporters group, and for these stakeholders, adopt the stakeholder engagement strategy defined for the project supporters.
  3. For these stakeholders, continue with the defined resisting stakeholder engagement strategy since this strategy has produced positive results so far.
  4. Transfer these stakeholders to the project supporters group but continue with the defined resisting stakeholder engagement strategy with these stakeholders.
Correct Answer

Q5. You are managing four projects in your organization. Two projects are of a similar type, but the other two are entirely different. What is your role in the organization?

  1. Portfolio manager
  2. Program manager
  3. Project manager
  4. Program coordinator
Correct Answer

Q6. To manage a project effectively, work should be broken down into small pieces. Which of the following does NOT describe how far to decompose the work?

  1. Until it has a meaningful conclusion
  2. Until it cannot be logically subdivided further
  3. Until it can be done by one person
  4. Until it can be realistically estimated
Correct Answer

Q7. During a team meeting, the team has been arguing about the method of integration for over 20 minutes without getting anywhere. The project manager reschedules the issue for the next team meeting. This is an example of:

  1. Compromising
  2. Forcing
  3. Smoothing
  4. Withdrawal.
Correct Answer

Q8. You are managing a project where your team is physically located with client personnel at a remote location. There is a high level of interaction between your team and client personnel, and client satisfaction is considered very important. Since the client is expressing a very high level of satisfaction with the project’s progress, your management has indicated no concerns about the project. However, you are behind schedule and over budget. In addition, morale among team members is low, and several team members have talked about quitting. Team members complain regularly about priority adjustments and alteration of activities. The weekly reports you receive about activities completed are often difficult to relate to the WBS and the project management plan. What action should you take to MOST effectively address these problems?

  1. You should enforce scope control.
  2. You should identify ways to make team members’ work more satisfying using the most applicable motivational theory.
  3. You should incur the extra expenses necessary to be on-site to more closely monitor the activities of the project team.
  4. You should create a reward and punishment system to ensure that project team members complete activities within the timeframes outlined in the project management plan.
Correct Answer

Q9. You are the project manager responsible for building a 100,000-squarefoot data center. One of the scheduled activities in your plan is to install the Computer Room Air Conditioning (CRAC) units. However, a raised floor must be installed in the data center before installation of the units can begin. This is an example of what type of precedence relationship?

  1. Finish to Finish
  2. Start to Finish
  3. Start to Start
  4. Finish to Start
Correct Answer

Q10. You are estimating the cost for your project by using historical data and applying it to your project, such as the cost of painting per square foot. Which technique are you using here?

  1. Bottom up
  2. Top down
  3. Analogous
  4. Parametric
Correct Answer