Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Diana is managing the development of a mobile phone application. Half the project work has been completed. Diana is currently reviewing her stakeholder engagement plan. She finds that some of the resisting stakeholders have now become supportive. How should Diana update her stakeholder engagement plan?
  1. Do not update the stakeholder engagement plan at this stage since things are getting better.
  2. Transfer these stakeholders to the project supporters group, and for these stakeholders, adopt the stakeholder engagement strategy defined for the project supporters.
  3. For these stakeholders, continue with the defined resisting stakeholder engagement strategy since this strategy has produced positive results so far.
  4. Transfer these stakeholders to the project supporters group but continue with the defined resisting stakeholder engagement strategy with these stakeholders.






Q2. While testing the strength of concrete poured on your project, you discover that over 35 percent of the concrete does not meet your company’s quality standards. You feel certain the concrete will function as it is, and you don’t think the concrete needs to meet the quality level specified. What should you do?

  1. Change the quality standards to meet the level achieved.
  2. State in your reports that the concrete simply “meets our quality needs.”
  3. Ensure that the remaining concrete meets the standard
  4. Report the lesser quality level and try to find a solution.
Correct Answer

Q3. Based on the chart, how is the project doing?

  1. You are in the trouble because there are three activities with no float
  2. You have a lot of flexibility because you have activities with float
  3. You do not have enough information to make a decision
  4. Everything is fine because you have an even number of activities with and without float.
Correct Answer

Q4. Analogous Cost Estimating is which of the following?

  1. Uses statistical relationship between historical data and other variables
  2. Generally less accurate
  3. Bottom-up estimating
  4. Generally accurate
Correct Answer

Q5. You are planning a storage device migration in a data center. During this phase of the project, who should control the project?

  1. Project Manager
  2. SMEs
  3. Sponsor
  4. Management
Correct Answer

Q6. A project manager needs to determine if the manufacturing process planned for the new micro-satellites will meet quality standards. Each satellite takes about three days to manufacture and costs US $125,000. The satellites are so small that inspection would destroy them. Under these circumstances, what should the project manager do?

  1. Outsource the inspection to another company with more expertise.
  2. Evaluate the attributes of the population.
  3. Inspect a sample of the satellites.
  4. Decrease the cost of quality.
Correct Answer

Q7. You are looking at the standard reports that the project management office has supplied, you see network diagrams and bar charts. In which of the following circumstances would you ALWAYS use a network diagram instead of a bar chart?

  1. To track progress or to report to the team
  2. To show logical relationships
  3. In the Define Activities process
  4. To report to senior management
Correct Answer

Q8. A team member comes to you (the project manager) privately and informs you that an employee of your customer is making unwelcome advances. The team member has repeatedly requested that this person stop, but the advances continue. What is the BEST course of action?

  1. Privatively confront the customer employee and threaten legal action if the advances do not stop.
  2. Suggest that the team member avoid contact with the customer employee.
  3. Contact the employee’s manager to arrange a meeting to discuss the matter.
  4. Facilitate a meeting with the team member, the customer employee, and yourself to allow the two to work it out amicably.
Correct Answer

Q9. After analyzing the status of your project, you determine that the earned value (EV) is lower than the planned value (PV). What should you expect as an outcome if this trend continues?

  1. The actual cost will be lower than planned
  2. The estimate at completion will be lower than planned
  3. The project will finish behind schedule
  4. The project will finish below the original cost estimate
Correct Answer

Q10. Key project stakeholders can significantly influence a project in many ways. During which stage of the project do these stakeholders have the maximum ability to influence a project?

  1. Planning
  2. Initiating
  3. Executing
  4. Monitoring & Controlling
Correct Answer