IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Based on the chart, how is the project doing?
Project Management PMP-5168.jpg
  1. You are in the trouble because there are three activities with no float
  2. You have a lot of flexibility because you have activities with float
  3. You do not have enough information to make a decision
  4. Everything is fine because you have an even number of activities with and without float.






Q2. Analysis of the scope performance resulted in a change request to the scope baseline. Change requests can include all the following except:

  1. Defect repair
  2. Supportive action
  3. Corrective action
  4. Preventive action
Correct Answer

Q3. A ______ is a collection of projects or programs grouped together for strategic business needs.

  1. Portfolio
  2. Management System
  3. Enterprise
  4. Array
Correct Answer

Q4. A new software development project is in progress and the project manager is working with the quality assurance department. They want to improve everyone’s confidence that the project will satisfy the quality standards. Which of the following MUST they have before they start this process?

  1. Completed checklists
  2. A quality control plan
  3. Results of quality control measurements
  4. Rework.
Correct Answer

Q5. All of the following are examples of the cost of non-conformance EXCEPT:

  1. Scrap
  2. Warranty costs
  3. Rework
  4. Quality training
Correct Answer

Q6. There have been numerous changes on your project. All approved changes are BEST reflected in the:

  1. Performance measurement variance
  2. Validate Scope process
  3. Change control procedures
  4. Project management plan
Correct Answer

Q7. You are using a technique involving the project’s risk and uncertainty to find the probability of completing the project under different situations. What process is this?

  1. Estimate activity duration
  2. Perform qualitative risk analysis
  3. Develop schedule
  4. Perform quantitative risk analysis
Correct Answer

Q8. The project is calculated to be completed four days after the desired completion date. You do not have access to additional resources. The project is low risk, the benefit cost ratio (BCR) is expected to be 1.6, and the dependencies are preferential. Under these circumstances, what would be the BEST thing to do?

  1. Cut resources from an activity
  2. Make more resources concurrent
  3. Move resources from the preferential dependencies to the external dependencies.
  4. Remove an activity from the project.
Correct Answer

Q9. The project manager of a highly visible project is new to project management. He has carefully followed the steps to create a project management plan. During a status meeting, two of the team members argue over what needs to happen next. Whose responsibility is it to correct the problem?

  1. The team
  2. The project manager
  3. The functional manager
  4. the individual team members who disagree
Correct Answer

Q10. Outputs of the Develop Project Team process are:

  1. Roles and responsibilities, project organization charts, and staffing management plan
  2. Project organization charts, project staff assignments, and roles and responsibilities.
  3. Project manager plan updates, staffing management plan, and project organization charts.
  4. Roles and responsibilities, staffing management plan, and resource availability
Correct Answer










User Agreement| |Privacy Policy