IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You are the project manager responsible for building a 100,000-squarefoot data center. One of the scheduled activities in your plan is to install the Computer Room Air Conditioning (CRAC) units. However, a raised floor must be installed in the data center before installation of the units can begin. This is an example of what type of precedence relationship?
  1. Finish to Finish
  2. Start to Finish
  3. Start to Start
  4. Finish to Start






Q2. You are working in a large organization and managing a project to construct a road. To help you in your project, your PMO is providing you with their support and require you to comply with them. What kind of PMO is this?

  1. Supportive
  2. Controlling
  3. Directive
  4. Helping
Correct Answer

Q3. As a project manager, you are presented with the following information on the net present value (NPV) of several potential projects. Which project is your BEST choice?

  1. Project A with an NPV $95,000
  2. Project B with an NPV of $120,000
  3. Project C with an NPV of $20,000
  4. Project D with an NPV of -$30,000
Correct Answer

Q4. Which of the following is an output of the Create WBS process?

  1. Scope baseline
  2. Project scope statement
  3. Decomposition
  4. Requirements documentation
Correct Answer

Q5. In the procurement process, the seller may be viewed initially as a bidder, then as the selected source, and then as the contracted supplier. The seller will typically manage the work as a project. In such an instance, which of the following is not true?

  1. The buyer becomes the customer and is then a key project stakeholder for the seller.
  2. Terms and conditions of the contract become key inputs to many of the seller’s management processes (ex: major deliverables, key milestones, cost objectives).
  3. There need not be a contractual relationship between the buyer and the seller.
  4. The seller’s project management team is concerned with all the processes of project management and not just procurement management.
Correct Answer

Q6. You are constructing an office building. The cost of this project is 200,000 USD, and the duration of the project is 8 months. During the performance review in the sixth month, you find that 65% of the work is completed and the cost performance index is 1.3. The Planned Value (PV) will be:

  1. 150,000 USD
  2. 130,000 USD
  3. 70,000 USD
  4. 266,666 USD
Correct Answer

Q7. Nate is the project manager for a research and development project. According to the project communication management plan, Nate has to call in weekly project progress update meetings. The last few meetings were a disaster since more time was spent in arguments and less on decisions. Which of the following techniques does Nate need to quickly acquire?

  1. Presentation techniques
  2. Listening techniques
  3. Writing style
  4. Meeting management techniques
Correct Answer

Q8. A project is considered out of control and the previous project manager has quit. You are assigned as the new project manager and have been asked to verify the quality level of the project and to recommend corrective action. What do you do FIRST?

  1. Review the project management plan
  2. Meet with the team
  3. Draw a control chart
  4. Create a risk mitigation plan.
Correct Answer

Q9. A rough order of magnitude estimate is made during which project management process group?

  1. Planning
  2. Closing
  3. Executing
  4. Initiating
Correct Answer

Q10. Crashing is an effective schedule compression technique at times when a project is struggling behind schedule. However, increasing the number of resources to twice the original number of the resources does not always cut the time by half. This is due to:

  1. Fast tracking the project
  2. Risk mitigation due to crashing the project
  3. The law of diminishing returns
  4. Critical path analysis
Correct Answer










User Agreement| |Privacy Policy