Project Management - Question 1:

A good friend at work tells you that when his wife was diagnosed with cancer, he stole items from work and sold them, using the money for her treatment. He has since paid back the money taken, in ways that kept his theft secret. Ethically, what should you do?

  1. Advise your friend to tell his company and do nothing
  2. Report him to his manager
  3. Talk with a lawyer to see if this can be justified
  4. Attempt to gather evidence to determine whether or not the theft in fact occurred.






Project Management- Q2. If a project manager wants to report on the actual project results vs. planned results, he should use a:

  1. Trend report.
  2. Forecasting report.
  3. Status report.
  4. Variance report.
Correct Answer


Project Management- Q3. Which of the following is not an interpersonal skill that the project manager will use to manage stakeholders' expectations?

  1. Active listening
  2. Overcoming resistance to change
  3. Punishment
  4. Building trust
Correct Answer


Project Management- Q4. Which of the following is the BEST method to make reward systems MOST effective?

  1. Pay a large salary increase to the best workers
  2. Give the team a choice of rewards
  3. Make the link between performance and reward clear
  4. Present notification of rewards within the company.
Correct Answer


Project Management- Q5. Based on the chart, what is the duration of a critical path?

  1. 30
  2. 23
  3. 49
  4. 46
Correct Answer


Project Management- Q6. Checklists, fishbone diagrams, and Pareto charts are ALL examples of:

  1. Tools used to define scope
  2. Tools used in quality management
  3. Tools used in team performance assessments
  4. Parts of a project management plan.
Correct Answer


Project Management- Q7. An output of Plan Procurements, the procurement documents are also an input to all of the following, EXCEPT:

  1. Approved Change Requests
  2. Administer Procurements
  3. Manage Project Team
  4. Conduct Procurements
Correct Answer


Project Management- Q8. Which part of the risk management process receives input from risk response owners?

  1. Identify Risks
  2. Perform Qualitative Risk Analysis
  3. Perform Quantitative Risk Analysis
  4. Plan Risk Responses.
Correct Answer


Project Management- Q9. All of the following are outputs of the Control Scope process EXCEPT:

  1. Change requests
  2. Updated organizational process assets.
  3. Updates to the project management plan
  4. Accepted deliverables.
Correct Answer


Project Management- Q10. Which of the following is NOT a factor in the project manager’s acquiring the best resources for the project?

  1. Schedule model
  2. Activity attributes
  3. Quantified resource requirements by activity.
  4. Directive of the project manager.
Correct Answer