IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

If a project manager wants to report on the actual project results vs. planned results, he should use a:
  1. Trend report.
  2. Forecasting report.
  3. Status report.
  4. Variance report.






Q2. James is managing a shopping mall construction project. During the project execution, he learns the project communications management plan is not effective and requires a major update. Which of the following processes will issue a change request for the required update?

  1. Plan Communications Management
  2. Manage Communications
  3. Perform Integrated Change Control
  4. Monitor Communications
Correct Answer

Q3. You just found out that a major subcontractor for our project consistently provides deliverables late. The subcontractor approaches you and asks you to continue accepting late deliverables in exchange for a decrease in project costs. This offer is an example of.

  1. Confronting.
  2. Compromise.
  3. Smoothing.
  4. Forcing.
Correct Answer

Q4. Lucy is managing a high-tech software development project. She has luckily acquired the organization’s best performing employees. However, the project team is not communicating effectively, causing delays. The project communications plan is in place, but it seems as if the employees are not following it. The communications plan lays out the communications requirements but does not explicitly assign responsibilities. What should Lucy do first? (Assume that all the following actions need to be taken at some stage.)

  1. Persuade the team to follow the plan
  2. Motivate the team to effectively communicate
  3. Set and manage expectations
  4. Resolve conflicts to prevent disruptive behavior
Correct Answer

Q5. Which of the following processes are usually not performed continuously, but rather, performed periodically as needed:

  1. Acquire Resources
  2. Monitor Risks
  3. Monitor Communications
  4. Monitor Stakeholder Engagement
Correct Answer

Q6. A tool that provides a visual representation of human resource allocation to a project, number of working hours, and availability on the project is a:

  1. Resource Histogram
  2. Staff release plan
  3. Resource Breakdown Structure (RBS)
  4. Organization Breakdown Structure (OBS)
Correct Answer

Q7. The list of identified risks is found in the risk register. However, the overall high-level project risks is first listed in the:

  1. Scope statement
  2. Requirement document
  3. Project charter
  4. Risk management plan
Correct Answer

Q8. Bill and Jake are two team members in a project. They do not get along well and are constantly involved in verbal conflicts. The project manager understands the characteristics of conflict and the conflict management process and tries to resolve the situation. Which of the following is not a correct statement?

  1. Openness resolves conflict
  2. Conflict is natural and forces a search for alternatives
  3. Conflict is inevitable in a project environment.
  4. The project manager is not responsible for conflict management.
Correct Answer

Q9. If you are managing changes to the project's cost baseline, which process are you using?

  1. Negotiate Costs
  2. Estimate Costs
  3. Control Costs
  4. Determine Budget
Correct Answer

Q10. You have been asked to determine the early start and finish dates for the activities that make up a project. What would be the BEST technique to use?

  1. Resource Smoothing
  2. Critical Path Method
  3. What-If scenario analysis
  4. Resource Leveling
Correct Answer










User Agreement| |Privacy Policy