Question:

James is managing a shopping mall construction project. During the project execution, he learns the project communications management plan is not effective and requires a major update. Which of the following processes will issue a change request for the required update?
  1. Plan Communications Management
  2. Manage Communications
  3. Perform Integrated Change Control
  4. Monitor Communications






Q2. Stakeholder notifications must be archived for future reference. Whenever the Manage Communications process produces a stakeholder notification, the notification must be:

  1. Updated to the organizational process assets
  2. Updated to the project management plan
  3. Updated to the project communications management plan
  4. Updated to the stakeholder register
Correct Answer

Q3. All of the following are inputs to the Determine Budget process EXCEPT:

  1. Activity cost estimates
  2. Work breakdown structure
  3. Project scope statement
  4. Project performance reviews.
Correct Answer

Q4. A company asks one of the project managers to lead a project to create a substantially improved version of one of the company’s best-selling products. The project manager is given total freedom of decision and resources, including whether to utilize contractor services and/or the company’s resource pool. Under these circumstances, which of the following would be the BEST way for the project manager to build the team?

  1. She should choose her team from the top developers and fabrication workers in the company
  2. She should create a team of company line workers and contract the development services under a cost reimbursable contract with provisions to protect confidentiality.
  3. She should contract the entire team utilizing a cost plus incentive fee type of contract.
  4. She should contract selected team members on an ad hoc and as needed basis utilizing a time and material contract.
Correct Answer

Q5. A quality management plan is created during which of the following?

  1. Project executing
  2. Plan Quality
  3. Manage Quality
  4. Perform Quality Control
Correct Answer

Q6. The project cost and schedule for deliverables can be reasonably estimated at what level of the WBS?

  1. The highest level
  2. The middle level
  3. The work package level
  4. Both A and C
Correct Answer

Q7. You are building a mile-long bridge on a T&M contract. During the excavation activity, you learned some telephone cables are crossing the alignment where you have to construct the bridge. You need to relocate these telephone cables, but there is no provision of such an activity in the contract. Further, the relocation of the cables is a costly task, and you need to do a lot of government paperwork, as well. You requested an amendment in the contract, but the buyer rejected it. Despite many efforts, you both could not resolve this issue. What should you do next?

  1. Terminate the contract following the termination procedures mentioned in the contract.
  2. File a judicial petition in accordance with the state’s law.
  3. Seek arbitration following the ADR procedures in the contract.
  4. Relocate the cables at your own expense since the contract does not cover this activity.
Correct Answer

Q8. You are a project manager for a small construction project. Your project was budgeted for US $72,000 over a six-week period. As of today, you have spent US $22,000. The earned value is US $24,000. According to your schedule, you should have spent US $30,000 by this time. Based on these circumstances, your project could be BEST described as:

  1. Ahead of schedule
  2. Behind schedule
  3. On schedule
  4. Having not enough information provided.
Correct Answer

Q9. Which of the following statements regarding team-building is correct?

  1. Team-building is essential during the middle of a project, and from there it is an ongoing process.
  2. Team-building is essential during the end of a project, and it is a one-time process.
  3. Team-building is essential during the end of a project, but it is an ongoing process.
  4. Team-building is essential during the front end of a project, but it is an ongoing process.
Correct Answer

Q10. A project manager has put in place rules covering who will have access to controlled documents, how changes to these items will be recorded and approved, and how everyone will know what the current version is. The project manager is therefore creating a:

  1. Work authorization system
  2. Change control system
  3. Configuration management system
  4. Project management information system
Correct Answer