Question:

A scope change has been suggested by one o the stakeholders on the project. After careful consideration and a lot of arguing, the change control board has decided to reject the change. What should the project manager do?
  1. Support the stakeholder by asking the board for the reason for the rejection.
  2. Suggest to the stakeholder that the next change they request will be approved.
  3. Record the change request and its result.
  4. Advise the change control board to make sure they create approval processes before the next change is proposed.






Q2. In a small office construction project, the following activities are scheduled in sequence. i) Digging and pouring footings: five days. ii) Working on the slab and pouring: three days. iii) Framing the floor: five days. iv) Wall framing: four days. v) Roof framing: six days. vi) Insulation and drywall: seven days. vii) Interior doors and trim: three days. viii) Hardware and fixtures: two days. What is the minimum time to complete the project if all activities are on a critical path except activity viii, and activity iii is delayed by one day?

  1. 32 days
  2. 33 days
  3. 34 days
  4. 35 days
Correct Answer

Q3. During the Manage Stakeholder Engagement process, a number of project documents might get updated. Which of the following project documents get updated the most during this process?

  1. Stakeholder register
  2. Risk register
  3. Project reports
  4. Project presentations
Correct Answer

Q4. An activity can be completed in 5 days if the conditions are favorable; however, if the conditions are unfavorable, it will take 10 days to complete. The most likely time for this activity to be completed is 6 days. Determine the PERT estimate for this activity.

  1. 6.5
  2. 7
  3. 5
  4. 3.5
Correct Answer

Q5. An experienced project manager was assigned a project of small scope. Which of the following could be true of the project?

  1. Defining Activities, sequencing activities, estimating activity durations, and developing the schedule could be viewed as a single process.
  2. Estimating activity durations may be skipped for the project.
  3. Developing and Controlling the schedule could be viewed as a single process.
  4. Defining Activities, estimating activity durations, developing the schedule, and controlling the schedule could be viewed as a single process.
Correct Answer

Q6. Which parts of the risk management process do not generally use organizational process assets as an input?

  1. Identify Risks and Perform Qualitative Risk Analysis
  2. Perform Qualitative and Quantitative Risk Analysis
  3. Perform Quantitative Risk Analysis and Plan Risk Responses
  4. Plan Risk Responses and Control Risks
Correct Answer

Q7. You are managing a multi-million dollar project that is a joint venture between your company and another organization. You have repeatedly tried to get the contact and the project charter finalized between the two organizations, but there has been a great deal of arguing over language and details. The project’s scope has been expanding, cost has been increasing, and the schedule has regularly been lengthening. You learn very suddenly that the project has been cancelled because the other organization withdrew its share of the funding for the project. What is the MOST likely reason that this occurred?

  1. Failure to understand the budgetary process
  2. Inadequate scope management
  3. Lack of sponsor commitment
  4. Poorly done initial cost-benefit analysis
Correct Answer

Q8. You are the project manager of a project. As part of the planning process, you use a planning technique to subdivide the project scope and deliverables into smaller, more manageable components. What is this technique called?

  1. Unit task analysis
  2. Decomposition
  3. Rolling wave planning
  4. Arrow Diagramming Method
Correct Answer

Q9. For projects where a business analyst collaborates with the project managers in managing the project scope, which of the following task is most likely to be performed by the business analyst?

  1. Acquire project resources
  2. Monitor the change control process
  3. Elicit, document, and manage stakeholder requirements
  4. Control project costs
Correct Answer

Q10. Lesley is managing a software development project for the World Climate Control Organization. Since her team members are dispersed across the globe, she would like to set up online conferences in the next two months to let everyone in her project know what is going on and what their roles are within the project. She wants to use these conferences as team development activities to learn and exchange information in the project. To schedule such activities, which of the following should she use to keep track of the availability of team members?

  1. Project charter
  2. Resource calendars
  3. Responsibility assignment matrix
  4. Project staff assignments
Correct Answer