IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

In an IT project, after several brainstorming sessions with customers, Kurt established various project deliverables. Two weeks later, while reviewing the plan, Kurt identifies two similar deliverables and decides to merge them into a single deliverable. What should Kurt do next?
  1. Merge the deliverables and inform the customer
  2. Submit the need to merge to the customer
  3. Merge the deliverables but do not inform the customer
  4. Merge the deliverables but do not update the project management plan






Q2. Long hours to meet a looming deadline and immense pressure for success from management are causing a decline in team morale. There are occasional conflicts between team members over priorities and resources. How should these non-disruptive conflicts be handled?

  1. Use of disciplinary actions
  2. Using a private, direct, and collaborative approach first
  3. Escalation to senior management
  4. Arbitration
Correct Answer

Q3. An issue has arisen which forces you to schedule a meeting with your stakeholders. A project team member tells you that one of your influential stakeholders may not come to the meeting because of a personal issue. You choose not to take any action because you think that you will manage without the presence of this stakeholder. What kind of risk response strategy are you using here?

  1. Accept
  2. Avoid
  3. Neglect
  4. Mitigate
Correct Answer

Q4. Which of these is not an established Estimate Activity Durations technique?

  1. Three Point Estimating
  2. Parametric Estimating
  3. Analogous Estimating
  4. Critical Path Estimation
Correct Answer

Q5. You are in the execution stage of your project, and you are informed that “corporate” will send in a team of consultants to review whether your project activities comply with your company’s and PMI’s policies, standards, and procedures. This is an example of:

  1. Quality Audit
  2. Organizational Process Assets
  3. Process Analysis
  4. Recommended Corrective Actions
Correct Answer

Q6. The approximate resource costs necessary for completing project activities are compiled during which project management process?

  1. Cost Reserve Analysis
  2. Estimate Costs
  3. Cost aggregation
  4. Forecasting.
Correct Answer

Q7. A project has the following risks: 20 percent probability of a 14 day delay in the receipt of customer requirements; 10 percent probability of a 21 day delay in the procurement process; 50 percent probability the integration will take 14 days longer. What is the expected monetary value of these events?

  1. 11.9 days.
  2. 35.8 days.
  3. 49 days.
  4. 7 days.
Correct Answer

Q8. A project manager is appointed to head highly technical project in an area with which this person has limited familiarity. The project manager delegates the processes of Develop Schedule, Estimate Costs, Define Activities, and Estimate Activity Resources to various project team members, and basically serves as an occasional referee and coordinator of activities. The results of this approach are likely to be:

  1. A team that is not highly productive, but that stays together because of the work environment created by the project manager.
  2. A team that is characterized by poor performance, low morale, high level of conflict and high turnover
  3. A team functioning throughout the project at a very high level, demonstrating creativity and commitment.
  4. A team that initially experiences some amounts of confusion but that after a period of time becomes a cohesive and effective unit
Correct Answer

Q9. The acceptable range of variation of a process is the ________ on a control chart.

  1. Mean
  2. Specification limit
  3. Rule of seven
  4. Upper and lower control limit.
Correct Answer

Q10. The communication model helps you communicate information to stakeholders smoothly. Which of the following is not a basic step in the communication model?

  1. Encode
  2. Transmit message
  3. Remove noise
  4. Decode message
Correct Answer










User Agreement| |Privacy Policy