IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

Your project sponsor has asked you to present your project’s high-level risk register to him in the next project update meeting. To create your high-level risk register, which of the following processes must be performed?
  1. Plan Risk Management
  2. Perform Qualitative Risk Analysis
  3. Identify Risks
  4. Monitor Risks






Q2. A first-time project manager is advised by an experienced project manager to plan for cost of quality. The first-time project manager is not sure which costs are included in the cost of quality. What would your advice be?

  1. Cost of quality only includes cost of nonconformance.
  2. Cost of quality includes cost of conformance and cost of nonconformance.
  3. Cost of quality only includes prevention costs and internal failure costs.
  4. Cost of quality only includes cost of conformance.
Correct Answer

Q3. You are managing a project with part-time resources in a weak matrix organization. Several of the team members attend team meetings and have not completed their activity assignments as scheduled. AT your next team meting, the MOST important agenda item would be:

  1. To review the work breakdown structure.
  2. Team building.
  3. To review project schedule and assignments.
  4. To define the impact of the delays.
Correct Answer

Q4. A project manager first creates an assumption log during the Develop Project Charter process and records all project assumptions and constraints. During which of the following processes is the assumptions log updated and/or new assumptions and constraints added during the project execution?

  1. Monitor and Control Project Work
  2. Close Project or Phase
  3. Direct and Manage Project Work
  4. Collect Requirements
Correct Answer

Q5. During project executing, the project manager is spending a lot of time solving problems that arise. It would be BETTER for the project manager to transfer his efforts to:

  1. Having the team solve the problems, thus freeing his time to hold more meetings
  2. Executing the project management plan and making sure the quality management plan is viable.
  3. Identifying additional risks and following the risk management process
  4. Performing sensitivity analysis on past problems and transferring them to other projects.
Correct Answer

Q6. A functional manager wants to change an activity estimate. The project manager analyzes the change and determines that it will cause a delay in the entire project. Who should authorize the change?

  1. Project team
  2. Sponsor
  3. Project manager
  4. Change control board
Correct Answer

Q7. As part of tracking a project, a project manager is validating the completion of project scope. He or she would measure this against:

  1. Requirements traceability matrix
  2. The Project Management Plan
  3. The Project Charter
  4. The requirements management plan
Correct Answer

Q8. All technical work is completed on the project. Which of the following remains to be done?

  1. Validate Scope
  2. Plan Risk Responses
  3. Create a staffing management plan
  4. Complete lessons learned.
Correct Answer

Q9. How does time-boxing help minimize scope creep in agile projects?

  1. It forces the team to create project WBS using the user stories.
  2. It forces the sponsor to allocate a Scrum master who helps in eliminating scope creep.
  3. It forces the team to process essential features first, then other features.
  4. It forces the team to convert the user stories into epics.
Correct Answer

Q10. What does a staffing management plan describe?

  1. When and how resources will be added and taken off the team
  2. How resources will be leveled
  3. What resources will be used on the project
  4. The responsible organization for each work package
Correct Answer










User Agreement| |Privacy Policy