Question:

Negative risks can either be ______, transferred, or mitigated as a countermeasure.
  1. enhanced
  2. avoided
  3. exploited
  4. ignored






Q2. You are taken to lunch by one of your sellers who has become a friend. He gives you an opportunity to participate in a new venture in association with his company, unrelated to your current employment. What should you do?

  1. Refuse to participate
  2. Participate
  3. Participate but advise your employer of the offer
  4. Request your employer’s consent for your participation.
Correct Answer

Q3. A manager asked to see a list of milestones in the project. This would be available as an output from the:

  1. Sequence Activities process
  2. Define Scope process
  3. Estimate Activity Durations process
  4. Define Activities process
Correct Answer

Q4. All of the following are inputs to the procurement process EXCEPT:

  1. Project scope statement
  2. Market conditions
  3. Product description
  4. Procurement statement of work.
Correct Answer

Q5. Developing alternative activity sequence is an example of:

  1. Risk transfer
  2. Risk aversion
  3. Risk identification
  4. Contingency planning
Correct Answer

Q6. A project manager is working with quality professionals in the Manage Quality process of the project. Which of the following activities is being performed?

  1. Perform Quality Control
  2. Determining if the right processes are being used
  3. Determining what processes should be used.
  4. Evaluating quality against the processes
Correct Answer

Q7. Which of the following is the BEST thing to do when asked to complete a project two days earlier than planned?

  1. Tell senior management that the project’s critical path does not allow the project to be finished earlier.
  2. Tell your boss.
  3. Meet with the team to look at options for crashing or fast tracking the critical path.
  4. Work hard and see what the project status is next month.
Correct Answer

Q8. Which of the following needs to be completed before resources can be finalized for the project?

  1. Work breakdown structure
  2. Estimates
  3. Bar chart
  4. Verify Scope
Correct Answer

Q9. While finalizing the WBS you assign each work package to a control account and establish a unique identifier for the same work from a code of account. These identifiers help you find a hierarchical sum of costs, schedule, etc. Which statement is true about the WBS?

  1. It contains all project work
  2. It authorizes the project manager
  3. It is a hierarchy of project staff
  4. It is a hierarchical breakdown of project resources
Correct Answer

Q10. Inputs to the Direct and Manage Project Work process include all of the following EXCEPT:

  1. Approved corrective actions
  2. Project management plan
  3. Implemented corrective actions
  4. Defect repair orders
Correct Answer