IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You are taken to lunch by one of your sellers who has become a friend. He gives you an opportunity to participate in a new venture in association with his company, unrelated to your current employment. What should you do?
  1. Refuse to participate
  2. Participate
  3. Participate but advise your employer of the offer
  4. Request your employer’s consent for your participation.






Q2. During the planning processes, activity G was estimated to take five days. Activity G is on the critical path. On day 2, it becomes clear that activity G will take 15 days, which will impact the imposed project end date. The project team meets to perform root cause analysis to identify the cause of the variance and to plan schedule recovery with activities performed later in the schedule. Which of the following should ALWAYS be of this kind of meeting?

  1. Recommend corrective action
  2. WBS updates
  3. Activity list updates
  4. Schedule updates
Correct Answer

Q3. Which of the following quality control tools and techniques may not be used for root cause analysis?

  1. Fishbone diagram
  2. Scatter diagram
  3. Ishikawa diagram
  4. Cause-and-effect diagram
Correct Answer

Q4. You have recently been assigned to a research project. Although there is a limited number of key stakeholders, there is a big number of other stakeholders involved in this project, especially the ones who will be using the research’s outcome. You have some specific questions. Which of the following is the best way to quickly obtain responses from a big group of stakeholders?

  1. Focus groups
  2. Questionnaires
  3. Interviews
  4. Phone calls
Correct Answer

Q5. Nancy's project is in execution. Nancy is currently planning to execute the Manage Stakeholder Engagement process. She has gathered the project documents such as the issue log, the change log, the stakeholder register, the lessons learned register and the necessary organizational process assets. Which of the following is a key input to this process that is still missing from this list?

  1. Expert Judgment
  2. Communication Skills
  3. Change requests
  4. Project Management Plan
Correct Answer

Q6. In quality terms, one of the meanings of “out of control” is:

  1. Someone on the team is upset
  2. A data point on a control chart falls inside the upper or lower control limit.
  3. Several data points on the same side of the mean within the upper and lower control limits.
  4. A data point is within 1 sigma.
Correct Answer

Q7. A project manager is taking over a project from another project manager during the planning process group. If the new project manager wants to see what the previous project manager planned for managing changes to the schedule, it would be BEST to look at the:

  1. Communications management plan
  2. Update management plan
  3. Staffing management plan
  4. Schedule management plan 71
Correct Answer

Q8. Which of the following is incorrect regarding a bidders conference?

  1. Questions from each seller should be handled confidentially and not shared with other sellers.
  2. No bidders should receive preferential treatment, even if they are part of the company's existing list of approved suppliers.
  3. Bidder conferences should not involve individual face-to-face meetings.
  4. All prospective sellers should be allowed to have a common understanding of the procurement.
Correct Answer

Q9. A project manager has put in place rules covering who will have access to controlled documents, how changes to these items will be recorded and approved, and how everyone will know what the current version is. The project manager is therefore creating a:

  1. Work authorization system
  2. Change control system
  3. Configuration management system
  4. Project management information system
Correct Answer

Q10. Which of the following processes produces a work breakdown structure as an output?

  1. Create WBS
  2. Define Scope
  3. Develop Project Management Plan
  4. Define Activities
Correct Answer










User Agreement| |Privacy Policy