IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

A critical resource is on another project team. It is essential that you get his time for your project. You have contacted the resource’s team manager several times but have received a poor response. What should you consider doing next?
  1. Plan for an alternate resource since this resource is not available.
  2. Try to use management influence to obtain the resource's time.
  3. Contact the manager once again to see if he can help.
  4. Train another resource within your project.






Q2. Henry is the project manager for a process improvement project. Henry is a recently hired Six Sigma expert. David is the process owner of the process Henry must optimize. During the project kick-start meeting with the project sponsor, David said he supports all continuous improvement efforts. However, David is unaware of the Six Sigma technique and feels threatened by the newly hired expert, and as a result, is blocking Henry’s ideas. What is David’s current engagement level with the project?

  1. Unaware
  2. Supportive
  3. Resistant
  4. Neutral
Correct Answer

Q3. You are assisting Benjamin, another project manager, to interview candidates for a resource position on his project. While reviewing your interview notes together, you notice that he sorts the candidate‘s resumes into two piles: One pile for further interviews, the other for candidates that did not meet the requirements for the position. You also notice that he has placed several of the highly qualified candidates in the second pile, stating that those interviewees "did not fit the corporate profile." Upon further review, you discover that all these candidates are of the same ethnic group. What do you do?

  1. Excuse yourself from the interviewing process
  2. Report this to the appropriate management
  3. File a complaint with PMI
  4. Do nothing
Correct Answer

Q4. If a project manager wants to report on the actual project results vs. planned results, he should use a:

  1. Trend report.
  2. Forecasting report.
  3. Status report.
  4. Variance report.
Correct Answer

Q5. You are just about to present your project’s status to your company’s executive team. Just as you are leaving your desk for the meeting, one of your resources hands you an updated report on the progress of a critical deliverable. As you are walking to the conference room, you review the report and notice there is an error in it. What do you do?

  1. Do not report on that part of the project
  2. Disclose that you have just discovered there is an error in some of the information you intended to present and only present the information that you know is true
  3. Cancel the meeting
  4. Present the information as-it-is and revise it in the meeting minutes, which will be sent after two days
Correct Answer

Q6. The project has been going well, except for the number of changes being made. The product of the project is being installed into seven different departments within the company and will greatly improve departmental performance when operational. The team has selected the appropriate processes for use on the project. The project manager is a technical expert as well as having been trained in communications and managing people. Which of the following is the MOST likely cause of the project problems?

  1. The project manager was not trained in understanding the company environment.
  2. The project should have more management oversight since it will result in such great benefits to the company.
  3. The project should have used more of the project management processes.
  4. Some stakeholders were not identified.
Correct Answer

Q7. Which of the following represents the value of work we have actually completed?

  1. Earned value
  2. Planned value
  3. Actual cost
  4. Estimate to complete 23
Correct Answer

Q8. If a project manager believes that a particular subcontract needs to be terminated, which of the following can provide guidance on the contract termination procedure?

  1. The contract termination procedures in the organizational process assets
  2. The termination clause of the specific subcontract
  3. The change control procedures in the project management plan
  4. The contract termination procedures in the project procurements management plan
Correct Answer

Q9. During the status review with your stakeholders, one of the stakeholders told you that they were not asked for their opinion, and now they need a change in the product characteristics. This change may lead to a change in your cost and schedule baseline. Which of the following processes could have helped you prevent this issue?

  1. Collect requirements
  2. Control scope
  3. Identify risks
  4. Scope creep
Correct Answer

Q10. You are a project manager of a complex project which involves many procurement contracts with subcontractors. During the execution phase, a subcontractor comes to you and says that he has completed his part of the work. You reviewed the facts and provided the subcontractor with a formal written notice that the contract has ended. What process is this?

  1. Validate scope
  2. Verify scope
  3. Close procurements
  4. Control procurements
Correct Answer










User Agreement| |Privacy Policy